1. What did I do yesterday?
- (susi_translator) - Updated Issue(#78) - 1. Replace -1 sentinel with HTTP status codes
open
- (susi_translator) - Updated PR (#76) - Refactor: RPC-style endpoints changed to REST conventions
open
- Merge branch 'main' into api-refactor (6/9/2026, 2:11:48 PM)
- Merge branch 'main' into api-refactor (6/9/2026, 5:04:40 PM)
- Fix transcript view validation and delete correctness (6/9/2026, 6:19:00 PM)
- (susi_translator) - Reviewed PR - #81 (implemented true multi tenant isolation and adjusted the configure endpoint, also updated the tests to verify strict memory boundaries)
open
Prepared all open PRs ready for merge, reviewing, merging conflicts, rebasing branches etc. Attended a meeting with mentors to discuss steps ahead and get deployment ready for the first prototype of SUSI translator.
2. What do I plan to do today?
Wrap up refactor issues, so we have clean endpoints to test in deployment.
3. What is blocking me from making progress?
No Blocker at the moment