The following CAPs have entered the Final Comment Period and will stay in this state for seven days where any major concerns that have not been previously addressed can be brought up. 

Concerns will be addressed on a case by case basis.

After a week of no major concerns, the CAPs will be marked as "Accepted" and head to implementation.


  1. CAP-51: add support for secp256r1 verification.
  2. CAP-53: create separate functions for extending the time-to-live for contract instance and contract code.
  3. CAP-54: lower total costs by refining the Soroban cost model used for VM instantiation into multiple separate and more-accurate costs.
  4. CAP-55: lower total costs by linking fewer host functions during VM instantiation in Soroban.
  5. CAP-56: lower total costs by caching parsed Wasm modules within a Soroban transaction.
Reference: CAP Process