FINAL REPORT CONTENT AND ASSIGNMENTS ( DRAFT FROM JULY 2008)
1. OVERVIEW: 2-3 pages Executive Summary, Introduction, and Conclusions
Drafted by subcommittee with Richard Ross, Christian Smith
2. CORRIDOR SUMMARIES 1-3 Pages per corridor
Summary, +/- Factors , Corridor Description, Survey/Interview results, Statistics
DRAFTED BY: Corridor Groups and leaders
3. Attachments to Corridor Summaries ( Letters, charts, etc)
DRAFTED BY: Corridor Groups and leaders
3. Compile and Organize All Photo Sets on Google Group
BY: Mike Smith-Lonergan
4. APPENDIX( Not published):
BY: Corridor Groups and leaders
Anyone who attends is a member of the Working
Group. We need more participants from all over Southeast, to review
the 10 proposed corridors in Southeast for public support, from Sandy
to Woodstock and from Milwaukie Ave to 82nd Ave.
Or you can pick up the Streetcar Workbook at SE Uplift, 9AM-3 Mon-Thursday.
Richard N. Ross, Southeast resident and planner, is the Working Group's volunteer facilitator.
All communications from the Working Group are posted at Google Groups "Streetcar System Plan SE Working Group" group.
Please sign up to receive meeting notes and work group documents:
http://groups.google.com/group/southeastpdxstreetcar?hl=en
To post to this group, send email to <southeastp...@googlegroups.com>
SE WORKING GROUP CORRIDOR ASSIGNMENTS
* Lead for Corridor Assessment
a. SANDY * David Amiton, Brendan Haggerty
b. BURNSIDE/28/GLISAN *Goudarz Eghtedari
c. BURNSIDE/STARK-WASHINGTON * Darrick Wong, Amanda Keppeler
d. BELMONT * Mike Smith Lonergan, Don Porth, Amanda Keppeler
e. HAWTHORNE/50TH * Paul Neidergang, Robin Smith, Bob Richardson,Peter Cowan
f. POWELL *Nelly Korn,Tim Joyce
g. FOSTER * Christian Smith, Peter Cowan, Bob Richardson, Walt Nichols
h. WOODSTOCK * Randall Magahay Rod Daggett 39TH Nelly Korn
i. MILWAUKIE-TACOMA *Tim Joyce
j. SE 82nd AVENUE (DROPPED) Nellie KornRichard N. Ross, AICP 2041 SE Elliott Ave. Portland, Or. 97214 H 503-235-8194 C: 503-807-0612 Fax: 503-235-8194