Hi Guys,
Here is the construction progress as per the updates received from my
Bro and Rajesh(Site engineer)
As of 9th May 2011:
Tile work:
- Vitrified tile work has started in second floor.
- Bathroom, pooja and kitchen tiles work ongoing in third
floor.
Plastering:
Inner walls:
- All floors completed. patch work is yet to be done after the
front wall plastering.
External walls:
- East,West and South wall work completed. North(Front) wall
work has started.
Wood work:
- started in ground floor.
Painting:
- all floors are done with one round of Prime.
- plastering completed exterior walls are primed with white.
Overall view:
The work progress has slowed down a bit and the completion dates
seem very challenging to accomplish.
Please update if any of you have recently visited the site.
Thanks,
Navnith
@Deiva,
Builder was mentioning to complete the work on time as promised
earlier. So no chance of further pushing.
On Apr 6, 9:35 pm, sudesh kumble <
sudeshkumble7...@gmail.com> wrote:
> Hi can anyone put light on this?
>
> On Thu, Mar 31, 2011 at 11:20 PM, sudesh kumble
> <
sudeshkumble7...@gmail.com>wrote:
>
> > Hi,
>
> > No problem, Thanks for the info Navnith. This is v helful for us. You know
> > wt we have shown the documents to our uncle who is a lawyer. But he said
> > there are few docs which is needed for further scrutiny like commencement
> > certificate, completion certification, EC, Khata extract, Khata certificate
> > & Building assesment certificate & tax paid. Our lawyer has said to take all
> > these doc from the builder. I have asked the builder about this.
>
> > Didn't your lawyer say about all these above docs? Did he give all these
> > docs to u?
> > Take care
> > Thanks
> > Sudesh K
>
> > On Thu, Mar 31, 2011 at 8:33 PM, Navnith <
navn...@gmail.com> wrote:
>
> >> Hi Sudhesh,
>
> >> Sorry for the late reply. I was bit occupied with office work.
>
> >> Here is the details you asked.
> >> On agreement I paid 32% of the amount as ready cash and the 18% on loan
> >> approval. I increased the cash component to get better price per square
> >> feet.
> >> Apart from there initial payments, there was a 20% settlement in Feb as
> >> per the payment schedule issued by builder.
>
> >> The next schedules are 10% in May, 15% on Flooring and Amenities
> >> completion and 5% on registration.
>
> >> Br,
> >> Navnith
>
> >> On Sun, Mar 27, 2011 at 1:12 PM, sudesh kumble <
> >>
sudeshkumble7...@gmail.com> wrote:
>
> >>> Thanks..can you just let us know how much % amt have u paid as per the
> >>> construction going? Rajdeep has asked us to pay 20% now
>
> >>> Just wanted to confirm and be safer. Pls guide us.
>
> >>> Thanks Navnith..
>
> >>> On Sat, Mar 26, 2011 at 7:19 PM, Navnith <
navn...@gmail.com> wrote:
>
> >>>> congrats dude..
>
> >>>> On Sat, Mar 26, 2011 at 2:00 PM, sudesh kumble <
> >>>>
sudeshkumble7...@gmail.com> wrote:
>
> >>>>> Hi,
>
> >>>>> Hey we have booked flat 305...
>
> >>>>> On Thu, Mar 24, 2011 at 8:20 AM, sudesh kumble <
> >>>>>
sudeshkumble7...@gmail.com> wrote:
>
> >>>>>> Hi Navnith,
>
> >>>>>> We were actually confused...as there is a party hall above tht floor
>
> >>>>>>>>
praveenr...@gmail.com> wrote:
>
> >>>>>>>>> another info...
> >>>>>>>>> i have told the site engineer that i would like to occupy some
> >>>>>>>>> where in july and asked him whether it will be completed by then...he said
> >>>>>>>>> everything will be done by that time for the flat except for lift, generator
> >>>>>>>>> etc(such common facilities)...
> >>>>>>>>> so hopefully they will complete everything at least by august....
>