> Below is the updated construction schedule for 13th Avenue.
>
> Friday 19th
> Dig up and repair areas east of the Ivy intersection
>
> Saturday 20th
> Pave areas repaired on Friday (base lift)
>
> Sunday 21st
> Pave areas repaired on Friday (base lift)
>
> Monday 22nd
> Overlay entire street section (no street parking)
>
> Tuesday 23rd
> Finish Overlay if not complete Monday (no street parking if needed)
>
>
>
>
> I will keep everyone notified with schedule updates as they occur.
>
>