Hi,
We have successfully placed the Tracker structure (PV supporting table) on the Roof using a crane. I thank Ravi, Rajiv, Firoz and Vivek for helping with the PV system dismantling and transfer to roof. I am grateful to all of them for their invaluable contribution.
Some work is still left....like installation of the tracker motor assembly (will require the 5th stub) and installing the panels.
Thanks once again.... I learned a lot working with you all....