Hello - Scrum says you can use schedule buffers as long as you're transparent in how you present them. �Do you have a standard set of schedule buffer factors you use on projects as needed? �For example, here's a set of schedule buffer factors I used on a previous project: ��Integration and iteration � Revisions and unforeseen requirements � Meetings and other supporting tasks � Standard max resource allocation of 80% per developer � Variable resource availability � Planned and unplanned PTO � Importance of completing on schedule Using a set of schedule buffer factors like this gives you a lot of lenience in applying the amount of buffer you feel is appropriate. For example, standard max resource allocation of 80%/developer (standard PM practice) gives you an automatic buffer of +20%. 1 day of planned or unplanned PTO per team member gives you another automatic buffer of +10%. Importance of completing on schedule is a weighted factor. �If it's not that important then you don't need to allocate much if any buffer for this. �However, if this is critical then you might want to allocate a buffer of up to 20% for risk management. Please let me know if you have a standard set of schedule buffer factors that you like to use as needed for Scrum projects....
Hello - Scrum says you can use schedule buffers as long as you're
transparent in how you present them. Do you have a standard set of
schedule buffer factors you use on projects as needed? For example,
here's a set of schedule buffer factors I used on a previous project:
@Ron - most processes have some amount of variation. Common causes for
this variation are usual, historical, quantifiable variations. As a
SM you might observe that although team members don't request PTO
before sprint planning, team members end up taking off an average of 1
day each before the end of the Sprint for planned and unplanned PTO.
If you don't account for variations like this up front then you're not
being realistic about a team's throughput capacity. Adding a buffer
item for "planned and unplanned PTO" is simply identifying a common
cause variation of the process that needs to be recognized and
understood. An additional advantage is that these buffer items can
also be used as problem statements for DMAIC....
Now that I think about it, a more Scrum-like approach could be to
display the common causes of variation on a flipchart during sprint
planning. Then using commitment-based planning, the SM could ask the
team to scan the flipchart of common causes of variation before
deciding whether to commit to an additional story....
Now that I think about it, a more Scrum-like approach could be to
display the common causes of variation on a flipchart during sprint
planning. Then using commitment-based planning, the SM could ask the
team to scan the flipchart of common causes of variation before
deciding whether to commit to an additional story....
@Ron - I'd like to get your feedback on my last post. It addresses 2
key challenges in Scrum:
* guiding the team without controlling the team
* approaches for delivery optimization
--
You received this message because you are subscribed to the Google Groups "Scrum Alliance - transforming the world of work." group.
To post to this group, send email to scruma...@googlegroups.com.
To unsubscribe from this group, send email to scrumallianc...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/scrumalliance?hl=en.