On 2012-02-14 19:06:13 +0000, Mike DiCenso said:
Agreed, though SLC-6 would have likely put a huge damper on things for
a while once the actual fueled testing of Columbia at that facility
revealed the flaws there.
I think that problem was trumped up by an Air Force that wanted out of Shuttle at all costs. This would not have caused significant launch delays.
No. External Tank production would probably have peaked around 18 per
year. Michoud could handle a little more, but I doubt they would have
really pushed that hard. They'd have reduced the flight rate to keep
things under control.
They'd have had no choice, looking back on it. There were other
technical issues that would have forced delays or flight rate
reduction or caused a catastrophic loss.
I really don't think any of the other problems rose to the level of the SRB field joint flaws, which had been showing signs of failure since STS-2. The other issues, like the Quick Disconnect, were theoretical or laboratory problems only, not actually seen in the real world. Fixes could have been implemented over time, just as the SSME and brake improvements were pre- and post-Challenger.
The biggest threat to flight rate was the cannibalization and spare parts issue, but as I wrote, that could have been resolved during the say, one year standdown while the field joint heaters are implemented, pending the full capture-feature redesign to follow a year or two later.
If not that many, a dozen? 15?
Probably, if they funded a third OPF at KSC (without sacrificing SLC-6.)
Would the agency order a
fifth shuttle with such demand?
No, they would have backed out of the commercial market anyway,
relieving pressure on the 24-per-year goal. Arianespace would have
taken more commercial payloads regardless of Challenger.
Why? STS had huge cargo capacity for most of the then existing
satellite classes. Just load up a bunch of satellites into one mission
as was done for STS-41-D.
It was proving complicated to get all the payloads ready at the same time. 41D itself was a an abberation caused by the cancelation of 41E (or was it 41F?) leading to that flight being combined with 41D after the RSLS abort in June. This is a continuing problem even today for Ariane 5, which is why all indications are that Ariane 6 will be an EELV-like one-at-a-time launcher. I suspect that even without Challenger, Shuttle would have seen a major decline in commercial payload launches, and NASA would not have complained all that much about Ariane 4 taking that business. Congress would have complained about the higher costs due to lower flight rate, but NASA would just have said "Sorry, Arianespace is underbidding us" and quietly walked away.
Brian
On 2012-02-15 01:56:55 +0000, bob haller said:
It was proving complicated to get all the payloads ready at the same
time. 41D itself was a an abberation caused by the cancelation of 41E
(or was it 41F?) leading to that flight being combined with 41D after
the RSLS abort in June. This is a continuing problem even today for
Ariane 5, which is why all indications are that Ariane 6 will be an
EELV-like one-at-a-time launcher. I suspect that even without
Challenger, Shuttle would have seen a major decline in commercial
payload launches, and NASA would not have complained all that much
about Ariane 4 taking that business. Congress would have complained
about the higher costs due to lower flight rate, but NASA would just
have said "Sorry, Arianespace is underbidding us" and quietly walked
away.
Brian
well the original plans for KSC included pad 39C as a matter of fact i
have seen a photo of a sign with C included.
They actually planned four pads at KSC. Four of everything, in fact:
Four High Bays in the Vehicle Assembly Building.
Four Mobile Launchers.
Four Firing Rooms in the Launch Control Center.
Four Launch Pads.
This was because originally they were expecting Earth Orbit Rendezvous to be the mode of travel to the Moon, and they thought that would mean two Saturn V-class launches per mission. So four of everything meant two missions could be prepped simultaneously.
When Lunar Orbit Rendezvous was chosen instead, the fourth of everything was defunded, with three of everything still going forward. A year or two later, Pad 39C and the third Firing Room wer also canceled, but we still got three High Bays in the VAB and three Mobile Launchers.
perhaps a additional pad would of been built?
The logjam wasn't the launch pads, it was the Orbiter Processing Facilites. KSC launched ten Shuttle flights in a one-year period (Jan 85-Jan 86) all from Pad 39A.
But neither additional OPFs or Pads would have solved the problem of finding three major payloads ready to launch at the same time.
Brian