3. At thhe outset, it is important for me to put on record the fact that We are fortunate to have been closely guided, administered and monitored by the ENC by their proximity and involvement. We are also fortunate for good financial grants both by the State Govt and MoD, due to which the school is in good shape. There is no dearth of money for all the infrastructure both capital expenditure and revenue/maintenance works.
4. The school had been getting adequate grants in aid both Non Plan and Plan. As a one time, I am giving the present status, for information of all. The aspect of sufficient funds being made available is evident from the balance of approximate funds and works in progress or being taken up till FY 2016-17 as under:-
Ser
Year
Non Plan/ Maintenance
Plan
Remarks
State Govt
1
2013-14
2.00 lakhs
Staff Room
2
2014-15
80.00 Lakhs
Dairy Farm Sheds, Gas Store, Laundry Sheds,Garbage Bins*, Firing Range Shed and Renovation of Auditorium
3
2015-16
1.00 Lakh
Band Uniform
4
Balance of above 3 years
41.00 Lakhs
Synthetic and Astro Turfing of Basket Ball, Volley Ball and Lawn Tennis Court with lighting
5
2016-17
516.00 Lakhs
Scholarship and Diet Supplement, Pension and Retirement Benefits, Maintenance of School Buildings, Electricity and Water Supply, Industrial Laundry Machine, Solar Water Tanks, Classroom Furniture, CC TV Network, Refrigerators for Cadets Mess, Guest Rooms, Display Boards, Plastic Molded Chairs and Ceremonial Stores,
Ser
Year
Non Plan/ Maintenance
Plan
Remarks
6
2017-18
516.00 Lakhs
Scholarships and Diet Supplement, Pension and Retirement Benefits, Maintenance of School Buildings, Infrastructure, Electricity and Water.
7
2010-11
11.00 Lakhs out of 335 Lakhs
Some Internal Roads*
8
2011-12
122 Lakhs out of 350 Lakhs
Palace I and II Floor Balance of Repairs
9
2013-14
350 Lakhs
Furnishing and Furniture for 32 New Staff Qrs, 8 House Masters Qrs and Other Staff Qrs Construction of Nursing Asst Qr and Construction of Boys House,
10
2014-15
350 Lakhs
Balance of Renovation of Palace including Gates, Underground Cabling, Construction of GE Qr, Balance of Auditorium Renovation and Construction of Furniture Yard.
11
2015-16
350 Lakhs
Relaying of Underground Water Pipe lines, Construction of Cadets Amenity Centre, Construction of 4 Blocks for Class IV employees and Balance of Repairs to 8 House Masters Qrs.
12
2016-17
350 Lakhs
Construction of General Employees Class IV Qrs
13
2017-18
350 Lakhs
Construction Of Administartive Staff Qrs and New Guest House, New School T Shirt, Durries and Replacement of Batteries
Ser
Year
Non Plan/ Maintenance
Plan
Remarks
MoD
14
2012-13
90.00 Lakhs
Horse Riding School including 6 Horses
15
2013-14
80.00 Lakhs
Construction of NDA Motivational Hall and Renovation of Toilets in 4 Cadets Hostels
16
2014-15
100.00 Lakhs
Provision of Additional Toilets in Cadets Hostels and Replacement of Ceiling Fans in Cadets Hostels
* Since Completed.
5. My main reason of giving the huge infrastructural plans is to guide the future batches to plan correctly whenever they do wish to donate or contribute to the School and at the same time also inform all that we have no role in accounting or execution of any projects.
6. Other Issue of General Imformation.
(a) Diet supplement increase from Rs 20/- to Rs 50/- is in advance stage with the state govt, because of which Diet Charges per day per Cadet will go up from Rs 70.50/- to Rs 85/-.
(b) Subject Experts are taking extra classes towards NDA training.
(c) Introduction of E Learning packages.
(d) Approval of long due honorarium to NCC ANOs by the State Govt.
(e) Gifting of Obsolete furniture to local schools through District Collector.
(f) All India Entrance Examinations change over to the OMR based Examination.
(g) Solar power plant (On Grid – 500KW) in school premises is an advance stage of discussions.
(h) Academics.
(i) AISSE (ClassX) pass percentage is 100 and school CGPA is 9.19.
(ii) AISSCE(Class XII) pass percentage 100.
(iii) School has emerged as the best amongst all Sainik Schools in AISSCE on the basis of Performance Index secured.
(j) NDA138, 37 out of 71 had cleared UPSC and 9 made in the merit list. NDA 139 35 out of 75 have cleared the UPSC exam and SSB are in progress. 81 cadets have appeared for NDA 140.
(k) Parent Teacher meetings have been held so far on 09 Apr and 23 July 2017.
(l) Sports.
(i) Inter House games and sports competitions are being held regularly.
(ii) 50 cadets took part in Olympic run held at District Level at Vizianagaram.
(iii) School achieved 1st Position in Volley Ball and Basket Ball; 2nd position in Foot Ball in the South Zone School Sports Tournament 2017.
(iv) 9 cadets participated in the District Level Athletics selection.
7. I am not able to enclose selected powerpoint slides of the co-curricular activities and extra-curricular activities for non-receipt of the same from the school due to some communication problems at the school due to the recent inclement weather conditions and the resultant problems.
8. Any other information of interest can be obtained from the school.
9. Lastly, if any Saikorian has any inputs for the overall improvement of school in any field, the same can be forwarded to me or one can even address the same to the Principal, Col R Atri, who is very receptive and a positive person.
Regards to all
Lt Gen K R Rao, PVSM,AVSM,VSM, (Retd)
Roll No 279