Hi Aditi,
I Had booked my flat in Aqua Casa project on 5th Oct 2012. It is almost 5 years
since the booking date & I see no clear signs of getting the project
delivered immediately.
We are already in talks with your management. The project has already been
delayed from your end and I am already bearing a huge interest on the Loan
availed from Bank in addition to the Rent of the apartment I am staying in
currently. The construction status of the site has not even reached 50%
while I have already paid around 85% of the total cost of the apartment. Till now i have made all the payment on time.Now it
seems that I have made a big mistake by investing in your project.
Please highlight on why this demand should be given when the project has not reached any stage even after the possession time has gone by long ago. Also, what are your plan to give us delay penalty. Also tell me how r u going to adjust delay penalty because after this demand only 5% amount will be left with us which is much less than the Delay penalty mentioned in RERA. Also clarify about the status of your registration in RERA and ESCROW account.
Till further notice, this demand is put on hold until we reach a stage of mutual understanding on the points above. I have invested my hard earned money and demand an explanation and penalty from you.. Any financial implication due to non-payment of this demand will be entirely on you
Dear Customer(s),
Greetings from Rudra...!!
“EVERY DROP COUNTS IN SEA”
Please be informed that Construction of Aquacasa is in full swing. Demand for External Plaster has been floated for the following towers :-
Tower Name
Date
T7
10-06-2017
T8
10-06-2017
We need funds to move man, materials & machines to deliver you the flats on deadlines. If you pay in time, we will mobilize resources to comply in time. Please help us to deliver.
If anybody will pay on or before 10th June’2017, we will give you an incentive of 1% of your demand amount, i.e., on the demand amount of “On Starting of External Plaster”.
If you clear your dues mentioned in demand note on or before 10th June 2017 in full, you will become eligible for 1% incentive and it will be credited in your flat account.
Please note the payment should be logged in with the clearance of books of accounts to Rudra.Looking forward to your response to timely payments.
"Shoot for the moon. Even if you miss, you'll land among the stars."
Bugga Aditi
Assistant Manager – CRM
Mob : 9560895646 |+91 120-4769950
E-mail ID: cr...@rudrabuildwell.com
website:www.rudrabuildwell.com
Thanks & Regard's,
Rawat Pooja