-original message-
Subject: [RR:157] FW: Quarry portion 26 of farm 22 Zouterivier - further questions
From: "Malachy Morrow" <mor...@altechisis.com>
Date: 16/03/2010 3:08 pm
Kapow.
Tx && rgds,
Mal
From: Ian Neilson [mailto:Ian.N...@capetown.gov.za]
Sent: 16 March 2010 02:56 PM
To: Malachy Morrow
Subject: FW: Quarry portion 26 of farm 22 Zouterivier - further
questions
FYI
Ian Neilson
Executive Deputy Mayor
Mayoral Committee member for Finance
Ward Councillor: Melkbosstrand / Blouberg West (Ward 23)
City of Cape Town
Cell 083 306 6730
Tel +27 21 400 1306
Fax +27 21 400 3368
email ian.n...@capetown.gov.za
________________________________
From: Johan Massyn
Sent: 16 March 2010 02:45 PM
To: Ian Neilson
Subject: FW: Quarry portion 26 of farm 22 Zouterivier - further
questions
FYI
Johan Massyn
District Manager: Roads and Stormwater
Ph 021 550 1045
Fax 021 550 7551
Cell 084 239 8817
________________________________
From: Colin Struthers
Sent: Tuesday, March 16, 2010 9:36 AM
To: Susan Matthysen; Katy Spalding; Morne Theron; Sharon Damon; David
Viljoen
Cc: Johan Massyn
Subject: RE: Quarry portion 26 of farm 22 Zouterivier - further
questions
Hi All Following legitimate complaints from various property owners
that use the servitude gravel track to access their properties and also
used by heavy vehicles to and from the clay mine, inspections were done
by Roads officials and it is confirmed that repairs are necessary in
order to restore accessibility by two wheel drive vehicles. In terms of
the Conditional Use approval conditions, your Directorate is requested
to instruct the applicant to immediately commence with repair work of
damage done by heavily loaded trucks and a tracked vehicle related to
the mining activity. Should immediate and effective repairs not be
undertaken by the applicant, T.R. & S. strongly urges your Directorate
to withdraw consent for the activity. Regards Colin
________________________________
From: Susan Matthysen
Sent: 15 March 2010 03:08 PM
To: Johan Massyn; Colin Struthers
Subject: FW: Quarry portion 26 of farm 22 Zouterivier - further
questions
Colin
Could you please provide the required input to get this matter finalized
Regards
Susan Matthysen
District Manager Blaauwberg
Planning & Building Development Management
CITY of Cape Town
TEL: 021 5501090
FAX: 021 5507517
________________________________
From: Sharon Damon
Sent: 15 March 2010 02:48 PM
To: Susan Matthysen
Cc: Katy Spalding; David Viljoen
Subject: FW: Quarry portion 26 of farm 22 Zouterivier - further
questions
Good Day Susan
I refer to our earlier discussion and per the subjoined e-mail could you
please intervene as with regards to this matter. We are still awaiting a
response from the Roads and Stormwater Department .We need to draft a
response to the complainants, who have already indicated that they have
escalated this complaint to a political sphere. We have served notice on
the owners for the non compliance of the LUPO conditions and will
forward this matter to court once the notice expires. We cannot do more
at this stage. However, we do require the input of the Roads and
Stormwater Department.
Thank you
Sharon Damon
Principal Property Inspector
2nd Floor Media City
cnr Hertzog Boulevard and Heerengracht
Cape Town
8001
Telephone No. 021 400 6451
Fax No. 0866973619
eMail : sharon...@capetown.gov.za
<mailto:sharon...@capetown.gov.za>
________________________________
From: Katy Spalding
Sent: Monday, March 15, 2010 11:00 AM
To: Sharon Damon; Johan Massyn; Benito Cogill
Cc: David Viljoen; Morne Theron; Colin Struthers; Susan Matthysen
Subject: RE: Quarry portion 26 of farm 22 Zouterivier - further
questions
Dear All
The e-mail below and the previous correspondence with Mr. Marrow,
refers:
In order to address the e-mail below and to avoid undue negative
publicity to the City due to inadequate monitoring of its LUPO
conditions, it is recommended that the information (points 1- 9 below)
be sourced as a matter of urgency, in order to determine the following:
1. Provide speedy and factual response to the complainant; and
2. Determine whether Council should act on Condition (q) of the
Conditional Use or approach legal services for a court interdict to
prevent further erosion from occurring on the road.
In view of the above it is suggested to co-ordinate our actions as
follow:
* The EHRM Department (this dept) to source the information for
points 1 - 3 (Katy Spalding);
* Road and Stormwater Department to source the information for
points 7 - 9 (Johan Massyn);
* Building Development Management (BDM) to inspect and verify
compliance with Point 6 (Benito Cogill);
Cleary Mr. Marrow has now escalated this complaint to the political
sphere. As such a response to the information requested should
preferably be provided as soon as possible. Can we therefore aim to
provide the same by Tuesday 23 March 2010, in order to address the
e-mail below from Mr. Marrow.
The opinion is held that the Land-Use Inspectorate (Sharon Damon) should
co-ordinate the proposed combined city response.
Regards,
Katy Spalding
Environmental Professional: Environmental & Heritage Management
District B & C
City of Cape Town
Milpark,
Milnerton
P O Box 35
Milnerton
7435
Tel: 021 550 1059
Fax: 021 550 1003
E-mail: katy.s...@capetown.gov.za
________________________________
From: Mal Morrow [mailto:malm...@gmail.com]
Sent: 12 March 2010 01:55 PM
To: Katy Spalding; Sharon Damon; Johan Massyn; David Viljoen
Cc: Rondeberg Road; Ian Neilson; Barbara Rass; Craig Lovett
Subject: Quarry portion 26 of farm 22 Zouterivier - further questions
Hello Ms Spalding, Ms Damon, Mr Massyn, Mr Viljoen -
Thanks for your previous attention.
I am reading the application for conditional use to permit clay mining
on Portion 26 of Farm 22 Zouterivier (attached) in closer detail, and I
find to my interest that the Council has a number of obligations. I
would like to be sure that the Council is fulfilling its obligation.
Please can you therefore supply the following material to me, that
correspond to the application that was granted:
1. A copy of the Environmental Management Plan as submitted and
supported by the Department of Mineral and Energy Affairs.
2. Written evidence that Cape Nature Conservation is satisfied with
this plan.
3. The name and contact details of the Council representative on
the Monitoring Committee, and complete minutes maintained by the Council
of meetings held by the Monitoring Committee.
4. Written evidence that waste and refuse disposal are to the
satisfaction of the Engineering Services Department.
5. Written evidence that water potability is to the satisfaction of
the Health Services Department.
6. Written evidence that ablution facilities meet the requirements
of the Engineering Services Department, the Executive Director: Health
and Housing and the National Building Regulations.
7. Written evidence that the upgrading and maintenance of the
existing access road is to a standard satisfactory to the Director:
Engineering Services.
8. Written evidence that the operator acknowledges legal
responsibility for the condition of the road.
9. Receipts and/or invoices of a financial guarantee made to the
Executive Director: Engineering and Planning in respect of maintenance
of the road, and evidence that this amount is still held by the Council
for the purposes defined.
As the application for a conditional use to permit clay mining on
Portion 26 of Farm 22, Zouterivier, was approved by the Council, then
all the above items are the obligations of the Council.
I therefore seek immediate reassurance that the Council is fulfilling
its obligations in respect of the conditional use.
Please supply me with the above items by return of email. If necessary,
you may post the evidence and material requested to my questions to the
below address, but please ensure that I am informed of the date of
postage by email or by phone.
Sincerely yours,
Mal Morrow
P: Caesura, PO Box 83, Philadelphia 7304
Land owner: Caesura, Portion 56 of Farm 22, Zouterivier, Klein
Dassenberg
C: +27 (84) 9944364
W: +27 (21) 4171849
F: +27 (86) 5114459
E: malm...@gmail.com
NOTE: This e-mail (including attachments) is subject to the disclaimer
published at: http://www.capetown.gov.za/en/Pages/disclaimer.aspx.
Please read the disclaimer before opening any attachment or taking any
other action in terms of this e-mail. If you cannot access the
disclaimer, kindly send an email to discl...@capetown.gov.za and a
copy will be provided to you. By replying to this e-mail or opening any
attachment you agree to be bound by the provisions of the disclaimer.
--
You received this message because you are subscribed to the Google Groups "Rondeberg Road" group.
To post to this group, send email to rondebe...@googlegroups.com.
To unsubscribe from this group, send email to rondeberg-roa...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/rondeberg-road?hl=en.
<<image001.jpg>>