Any Updates

10 views
Skip to first unread message

mohankrishna kavali

unread,
Apr 7, 2014, 10:53:11 AM4/7/14
to rhymer-eas...@googlegroups.com
Hi All,

Anyone got the updates?

Amar Ellareddy

unread,
Apr 18, 2014, 2:24:40 AM4/18/14
to rhymer-eas...@googlegroups.com
Can some one take few mins to update the meeting discussion, appreciate your time.

Ranjini

unread,
Apr 20, 2014, 12:46:32 AM4/20/14
to Amar Ellareddy, Rhymer Easton Villas
The request to do the change of land use is obtained by Rhymer now. This is the one that was taking time.
Now they will actually do the conversion and after that get the BMRDA approval. They said that things can happen only after election and would take another 3 months ...
@Others in the group : If I have missed out on anything, plz add ...

Rajashekhar Gundegowdar

unread,
Apr 20, 2014, 1:16:47 AM4/20/14
to Ranjini, Amar Ellareddy, Rhymer Easton Villas

Dear Ranjini

Thanks for updates.

###################
Rajashekhar Gundegowdar
09900235982

Amar Ellareddy

unread,
May 24, 2014, 1:55:01 AM5/24/14
to rhymer-eas...@googlegroups.com
Hi All, Election code is over, I think we should start interacting with developer to get concrete plan. It is been more than year now.

Aravind S

unread,
May 25, 2014, 1:45:52 PM5/25/14
to Amar Ellareddy, Rhymer Easton Villas
Hi All,

 Shall we plan to meet Rhymer on coming or next Saturday?

Thanks,
S. Aravind


On Sat, May 24, 2014 at 11:25 AM, Amar Ellareddy <aella...@gmail.com> wrote:
Hi All, Election code is over, I think we should start interacting with developer to get concrete plan. It is been more than year now.



--
Thanks and Regards,
Aravind Sundararaj
+91-9686946914

Indra Sahu

unread,
May 26, 2014, 3:26:36 AM5/26/14
to Aravind S, Amar Ellareddy, Rhymer Easton Villas
Hi all,

It is learnt that wire fencing/ boundary work is being done, however, it will be wise deceision to have a meeting with Rhymer,in early next month.

Thanks

I C Sahu

Mohammed Anzy S

unread,
May 26, 2014, 3:27:53 AM5/26/14
to Indra Sahu, Aravind S, Amar Ellareddy, Rhymer Easton Villas
who said about the wire fencing work ? Did anyone see it ? i was there last week and i did not see anything
--
Cheers,
Anzy

Aravind S

unread,
May 26, 2014, 3:31:40 AM5/26/14
to Mohammed Anzy S, Indra Sahu, Amar Ellareddy, Rhymer Easton Villas
Hi,

 Month before communication from  Umeir was, the fencing work has started and will be done in 15 days. hopefully It is done, if not need to check with umeir.

Thanks,
S. Aravind

Ranjini

unread,
May 26, 2014, 5:37:43 AM5/26/14
to Aravind S, Mohammed Anzy S, Indra Sahu, Amar Ellareddy, Rhymer Easton Villas
I spoke to Umair yesterday and he said that they have some meeting with the BBMP on Thursday and that he will update after that on the next steps .

Ravi Jandial

unread,
May 26, 2014, 5:50:18 AM5/26/14
to Ranjini, Aravind S, Mohammed Anzy S, Indra Sahu, Amar Ellareddy, Rhymer Easton Villas
Is it BBMP or BMRDA ?? Rhymer Easton location doesnt come under BBMP limits. Also, I dont think boundary wall for a 46 acre property can be constructed within 15 days.

Ranjini

unread,
May 27, 2014, 9:18:47 AM5/27/14
to Ravi Jandial, Aravind S, Mohammed Anzy S, Indra Sahu, Amar Ellareddy, Rhymer Easton Villas

It should b bmrda only n not bbmp. ..

Ravi Jandial

unread,
May 30, 2014, 10:17:17 AM5/30/14
to Rhymer Easton Villas
Any further update ? Has the boundary wall construction started ? And is the land now residentially converted ?

Mohammed Anzy S

unread,
May 30, 2014, 10:28:52 AM5/30/14
to Ravi Jandial, Rhymer Easton Villas
no boundary and nothing . I had gone there today
--
Cheers,
Anzy
Reply all