Dear All,
Todays MOM points are as below
1. Currently land acquisition / registration from farmer to investor (rhymer mediator) is in progress. Till December around 50-60% land registration will be over. As evidence they shown us some land papers already registration is done.
2.yet to done CLU (change of land use) and Clearance certificate. This also will happen once registration over. Both CLU and Clearance will be done parallel.
3.lot of paper work and legal documentation is happening. Checking all the family history of farmers, to avoid future conflicts. The big challenge is to convince the farmers/ owners to sell.
4. By the end of JANUARY, expected to start actual ground work on site.
5.Last and good point is they are very much Confident on this project and agreed that the unexpected delay due to various govt. procedure/process.
If I missed any point please kindly add.
Thanks
-Krishna