work stopped at construction site

69 views
Skip to first unread message

RK3024

unread,
Jun 17, 2014, 11:33:03 PM6/17/14
to queensgate-house-of-...@googlegroups.com
I came to know this from another group that construction work is stopped for existing apts since past few days.
When I visited the site, I was told that it will resume on monday(Jun 16). Any updates on this ? How does this impact us ?

Thanks
Ravinder

Chetan Kulshrestha

unread,
Jun 20, 2014, 11:19:34 AM6/20/14
to queensgate-house-of-...@googlegroups.com
That's bad news, I have asked from CRM team, lets hope they reply at least.

Is there anyone in our group who is in Bangalore right now?

Regards
Chetan Kulshrestha

Nivi Nishant

unread,
Jun 22, 2014, 4:45:46 AM6/22/14
to Chetan Kulshrestha, queensgate-house-of-...@googlegroups.com
My Brother In Law went to the site yesterday and even he told the construction is stopped.
When asked, he was told that the construction is halted for last 3 days but they will start soon.
Got all vague answers - didnt confirm why it stopped, when it's gonna start again.



--
You received this message because you are subscribed to the Google Groups "Queensgate House of Hiranandani Bangalore" group.
To unsubscribe from this group and stop receiving emails from it, send an email to queensgate-house-of-hirana...@googlegroups.com.
To post to this group, send email to queensgate-house-of-...@googlegroups.com.
Visit this group at http://groups.google.com/group/queensgate-house-of-hiranandani-bangalore.
For more options, visit https://groups.google.com/d/optout.

chetan. kulshrestha

unread,
Jun 23, 2014, 6:42:50 AM6/23/14
to queensgate-house-of-...@googlegroups.com
Hi Guys,

          Just got the reply from CRM team.

"

Dear Customer,

 

As you may already be aware, due to some unforeseen circumstance, there has been a temporary stoppage of work at Bannerghatta site. We would like to take this opportunity to dispel certain rumors that have surfaced over the last few days.

 

First and foremost we would like to assure you that the land parcels are owned by the Company. The title for these parcels has been checked and vetted by two large and well represented legal firms, as well as lawyers representing financial institutions that have approved our project for home loans.

 

Secondly, we would like our customers to know that we are attending to this issue very seriously. It is evidently a case of blackmail and extraction as our project gains prominence for finishing and quality.

 

We recognize and fully appreciate the kind of anxiety you must be under in the present circumstances. We invite you to get in touch with the undersigned for any queries you may have. Me and my team are dedicated to assuring you of the safety and security of your investment.  Please be assured that we will keep you posted on the developments.

 

Regards,

"





Regards
Chetan Kulshrestha




On Wednesday, 18 June 2014 04:33:03 UTC+1, RK3024 wrote:
Message has been deleted

Saif

unread,
Jul 23, 2014, 7:45:49 PM7/23/14
to queensgate-house-of-...@googlegroups.com
Work has resumed at site