Scope and Timeline for Puppet Platform 5.5.1

10 views
Skip to first unread message

Kenn Hussey

unread,
Mar 21, 2018, 10:28:54 AM3/21/18
to puppe...@googlegroups.com
Now that Puppet Platform 5.5.0 has shipped, I would like to draw your attention to the scope and timeline for our next monthly release, Puppet Platform 5.5.1.

Scope

The scope of this release includes fixes for security vulnerabilities and problems with Puppet Platform 5.5.0 that are found by the community. Code for this release should land on the ‘5.5.x’ branch (and corresponding component branches) for puppet-agent, ‘5.2.x’ branch for PuppetDB, and ‘5.3.x’ branch for Puppet Server.

Timeline

The “String Freeze” milestone for this release is targeted for April 6. This is the date by which all changes affecting translatable strings must be complete (so that we have time to request, obtain, and merge translations before we ship).

The “Stop Ship Line” milestone, by which time all planned code changes must be complete, is targeted for April 11.

This means that all work for the release needs to be planned during the next three weeks, with the goal of shipping the release on April 17.


If you have any questions or concerns about any of this, please let me know.

Thanks,

--
Kenn Hussey
Program Manager, Puppet Platform

Reply all
Reply to author
Forward
0 new messages