Scope and Timeline for Puppet Platform 5.5.13

5 views
Skip to first unread message

Nirupama Mantha

unread,
Mar 29, 2019, 1:39:28 PM3/29/19
to puppe...@googlegroups.com

Now that Puppet Platform 5.5.12 (was 5.5.11) has been released, I would like to draw your attention to the scope and timeline for the next release in the 5.5.z series, Puppet Platform 5.5.13.


Scope


The scope of this release includes fixes for security vulnerabilities and problems with Puppet Platform 5.5.12 that are found by the community. Code for this release should land on the ‘5.5.x’ branch (and corresponding component branches) for puppet-agent, ‘5.2.x’ branch for PuppetDB, and ‘5.3.x’ branch for Puppet Server.


Timeline


The “String Freeze” milestone for this release is targeted for March 29. This is the date by which all changes affecting translatable strings must be complete.


The “Stop Ship Line” milestones, by which time all planned code changes must be complete, are targeted for April 2 (puppet-agent) and April 3 (PuppetDB and Puppet Server).


This means that all work for the release needs to be planned during the next two weeks, with the goal of shipping the release on April 16.



If you have any questions or concerns about any of this, please let me know.


Thanks,


--

Nirupama Manthahttp://www.puppet.com | 
Senior Technical Program Manager 

Reply all
Reply to author
Forward