Dear All,
The points from the previous email that needs to be discussed are
 
1. What is the logic for arriving at the electricity rates of 7.57 for EB and 18.95 for GB.
2. When do we get electricity bills for the month of April, May and June ?
3. We were told that the generator electricity would be Rs. 15/KWH and this has not been respected.
 
 
the new points that need to be discussed are
 
1. The UPS issues with lifts- Need form date.
 
Please add/suggest further points ...max 5 that can be taken on high priority and has the biggest impact.
 
 
Regards,
Gautam
 
 
 
 
 
----------------

Minutes of meeting- 21st June

To
Dear All,
The minutes of the meeting that happened on 21st June are as given below. The response from Preserv has been captured in line with the points given below.
1. The security check at the gate is causing trouble to the residents. The guards should not open the dickey of the residents.
[Preserv] Agreed that this would be discontinued.
2. The residents do not have a clarity on the DG rates that would be charged.
[Preserv] The DG rates have been provided to the residents.
3. What is the formula for arriving at the DG and EB consumption given the fact that the meters in some apartments do not show the separate readings.
[Preserv] The ratio or the proportion of the consumption would be taken into account by reading the meter reading of towers in which the meters have been provided that shows separate readings.
4. When would the new meters be in place which can record the DG and EB consumption
[Preserv] Updated to the residents that this would be completed in next one week for all towers.
5. Updates on Lawn Tennis courts, kids play area
[Preserv]Lawn Tennis courts would be ready in one month time frame. There have been issues with the vendor supplying the equipments for play area and a new vendor has been finalised. This will take some time and hopefully in the next 1.5 months this should be ready.
6. Currently Airtel as an ISP exists. Discussed if we can have other ISP's and Tata Sky as a vendors.
[Preserv] Preserv will look into it and will come back with an update in the next 15 days.
@ Dear Mr. Hari Sharma, please feel free to add/update your comments.
Regards,
Gautam

Vasdev, Anuj Kumar

unread,
Jun 27, 2014, 3:17:01 AM6/27/14
to spazep...@googlegroups.com, Privys...@googlegroups.com, krsi...@yahoo.co.in, nitin_...@yahoo.com, sonal...@gmail.com

Thanks Gautam !

 

I think we can add another point as

 

(4) Car parking allocation in the Basement and its cleaning

 

(5) TV Connection options

 

Thanks, Anuj

--
Join us on facebook Page - https://www.facebook.com/Spazeprivy72
---
You received this message because you are subscribed to the Google Groups "SpazePrivy72" group.
To unsubscribe from this group and stop receiving emails from it, send an email to spazeprivy72...@googlegroups.com.
To post to this group, send email to spazep...@googlegroups.com.
Visit this group at http://groups.google.com/group/spazeprivy72.
For more options, visit https://groups.google.com/d/optout.rs

Reply all
Reply to author
Forward
0 new messages
Search
Clear search
Close search
Google apps
Main menu