There will be periodic closures of Alexander Rd., where it crosses the creek and canal.  Here is what Princeton municipality says:

As part of the Alexander Street Bridge Replacement Project, PSE&G, Comcast, Crown Castle, and Verizon will be relocating their overhead facilities on Alexander Street in the Municipality of Princeton.  PSE&G will need full lane closures from March 16 through March 24, weather permitting.  The closure will be from 9am-2pm on week days and 8am-2pm on weekends.

Once PSE&G has completed their work, Comcast is next, followed by Crown Castle and then Verizon.  It is anticipated that the other utilities can complete their work using an alternating traffic pattern.