You are the manager of your company’s project management office (PMO). In this role you hold regular meetings with each project manager on your team to determine how they are doing and what the status is of their projects. During a recent meeting you were told by a project manager that one of her project’s actual cost is 20% under planned cost. What is the BEST feedback you can provide?
a. Ask her if this includes indirect costs
b. You expect the project will complete under budget.
c. An increase in costs later in the project will more than likely bring the budget closer to estimates.
d. She should do a better job of estimating in the future
Answer: A
Explanation: A project’s actual or direct costs are very different from indirect costs. Indirect costs are those that are not directly attributable to a single project and are spread out across the entire portfolio. However, a project manager may include them. As a result, the correct feedback is Option A, you need to fully understand her costs to determine how the project is performing . Option B cannot be determined using the information provided. Although Option C may actually be a possibility it, but again, at this point you don’t know if the project manager is including indirect costs or not. Option D is not applicable since you don’t really know this is the case. PMBOK 4th Edition Pg. 173
----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Your complete Earned Value calculations. Your CPI is less than 1. Which of the following options should you take first?
a. Eliminate risks in current estimates
b. Meet with the sponsor to find out what work can be fast tracked
c. Reduce quality
d. Cut some scope
Answer: A
Explanation: With a CPI < 1, you have cost overruns. Reducing quality and cutting scope should not be the initial action you take as PM. Fast tracking may not help your costs either and you may introduce re-work; costing you even more! Your best bet is to look at your estimates and work to remove risks from these to reduce costs. Once this is done you may decide to take further action like reducing scope or quality via formal Change Control process.
On Friday, 24 August 2012 16:53:32 UTC+5:30, Binoy wrote: