Hi All,
The following PMP® exam sample question is taken from the Free PMP Exam Simulator at
http://free.pm-exam-simulator.com - The answer is at the very bottom:
------------------------------
The
type, quantities and assumptions made in determining the resources,
basis of estimate for each resource, and availability of resources for
each activity or work package is identified in which of the following
documents?
A.) Resource Breakdown Structure
B.) Responsibility Assignment Matrix
C.) Resource Calendars
D.) Activity Resource Requirements
------------------------------
Hint:
Carefully read the question. The question is asking for assumptions
made in determining the resources, as well as the basis of estimates.
This happens in the Estimate Activity Resources process. Think about the
outputs of this process.
------------------------------
All our questions are updated to the latest PMBOK® Guide standard. Stop by at
http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at
http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.
Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC
The Project Management PrepCast™ -
http://www.project-management-prepcast.com
The Project Management Podcast™ -
http://www.project-management-podcast.comANSWER AND EXPLANATION:
The correct answer is D
Explanation:
The type, quantities and assumptions made in determining the resources,
basis of estimate for each resource, and availability of resources for
each activity or work package is identified in the Estimate Activity
Resources process. Resource Calendars identify only type, quantity,
availability, and capabilities of resources.
Reference: PMBOK Guide 4th Edition, page 145