Valuable One Page PMP Exam Formula's

0 views
Skip to first unread message

PMP Exam Resource

unread,
Nov 3, 2009, 10:30:25 PM11/3/09
to pmp-pre...@googlegroups.com
Dear Group Member,

This is a One Page Formula's for PMP Exam that will help you for quick reference before the exam.
------------------------------------------------------------

Q U A L I T Y
-------------
CoQ = ( ( Review Efforts + Test Efforts + Training Efforts + Rework Efforts + Efforts of Prevention) / Total Efforts) x 100 %

PERT = O + 4ML + P
--------------
6
MEAN -> Average

MODE -> The “most found” number

RANGE -> Largest - Smallest Measure.

MEDIUM -> No in the middle or avg. of 2 middle Nos

STD. DEV. OF TASK = P - O
____________
6

TASK VAR. = (P – O) 2 = Std. Dev ^ 2
____________
6
_____________
CP STD. DEV. = √ σ² + σ² + σ²

SIGMA 1 = 68.26
2 = 95.46
3 = 99.73
6 = 99.99


Channels of Communication
-------------------------
COMM = (N2 - N) / 2 = (N x (N – 1)) / 2


P R O J E C T S E L E C T I O N
---------------------------------
PV = F V .
-------
(1+r)ⁿ

FV = PV x (1+r)

NPV = S ( PV + PV + PV + PV )
---- ---- ---- ----
(1+r)ⁿ (1+r)ⁿ (1+r)ⁿ (1+r)ⁿ

Cash Flow = Cash Inflow – Cash Outflow

Discounted Cash Flow = CF x Discount Factor

ARR = S Cash Flow / No. of Years

ROI = (ARR / Investment) * 100 %

BCR = Benefits / Cost

Exp. Value = Probability % x Consequence $


Class of Estimates
-------------------
Definitive +5%

Capital Cost +10-15%

Appropriation +15-25%

Feasibility +25-35%

Order of Magnitude > +35%


Contract Incentives
--------------------
Savings = Target Cost – Actual Cost

Bonus = Savings x Percentage

Contract Cost = Bonus + Fees

Total Cost = Actual Cost + Contract Cost


E A R N E D V A L U E A N A L Y S I S
---------------------------------------------
PV (Present Value) = BCWS (Budgeted Cost of Work Schedule)

EV (Earned Value) = BCWP (Budgeted Cost of Work Performed)

AC (Actual Cost) = ACWP (Actual Cost of Work Performed)

CV = EV – AC

CPI = EV / AC (efficiency)

SV = EV – PV

SPI = EV / PV

ETC = BAC – EV or (BAC – EV) / CPI

EAC = AC + ETC

EAC = BAC / CPI

VAC = BAC – EAC

% COMPLETE = EV / BAC x 100

% SPENT = AC / BAC x 100

CV% = CV / EV x 100

SV% = SV / PV x 100

------------------------------------------------------------

GoodLuck,
PMP Resources

P.S: HIGH DEMAND RESOURCES FOR PMP EXAM

Get Least Expensive 35 Contact Hours
from the comfort of your home
http://pm-best.com/page.php?2

---->Discount Resources<----

Link shorten for your convenience
'Feel free to share it, tweet it, blog it'

http://bit.ly/pmprepcast PM PrepCast Get 35hrs-Cheapest Way
http://bit.ly/pmformulas PMP(r) Exam Formula Study Guide
http://bit.ly/pmflashcard Over 1750+ PMP(r) Exam Flash Cards
http://bit.ly/ritatestdisc Rita Simulation Fastrack Discount
http://bit.ly/certtest4thedi Cert Champ PMP Exam 4th Ed Test Free
http://bit.ly/ritabkdisc Rita Mulcahy PM Prep
http://bit.ly/pmbokbkdisc PMBOK(c) 4th Edition
http://bit.ly/pmbokqadisc PMBOK(c) PMI's Official Qs Ans
http://bit.ly/crossbkdisc CrossWind PMP Exam Success Series
http://bit.ly/kimguidebkdisc Kim Heldman - PM Study Guide
http://bit.ly/pmstar PM-Star - Gear Up for PMP Exam (Qs & Training)

Download PMP Exam Secrets Now
http://webmasterstreasure.com/recommends/pmp5secrets

Lowest Price PMP Resources
http://tinyurl.com/456so

Free Viral Twitter Blaster Software
Earn $4000 and 9990+ followers per month
on Auto Pilot
http://bit.ly/33vUn

Reply all
Reply to author
Forward
0 new messages