to Enterprise-Pro...@googlegroups.com, Gabl...@googlegroups.com, International-Pr...@googlegroups.com, pmi...@googlegroups.com, PMI-...@googlegroups.com, PMI-PCC-Ref...@googlegroups.com, PMI...@googlegroups.com, PMI...@googlegroups.com, PMP-...@googlegroups.com, PMP-Pre...@googlegroups.com, PMP_...@googlegroups.com, PMP...@googlegroups.com, PMPI...@googlegroups.com, PMPL...@googlegroups.com, pm...@googlegroups.com, Project-M...@googlegroups.com, Project-Management-...@googlegroups.com, Project-Manageme...@googlegroups.com, Project-Management-...@googlegroups.com, Project-Management-Practices-T...@googlegroups.com, Project-Manage...@googlegroups.com, project-...@googlegroups.com, ProjectM...@googlegroups.com, Proje...@googlegroups.com, proj...@googlegroups.com, rochelle...@osp-international.com, Software-Proj...@googlegroups.com, TeamPM...@googlegroups.com, vn...@googlegroups.com
Hi All,

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

Activity / Duration / Predecessor
A / 2 / Start
B / 4 / A,E
C / 6 / A
D / 3 / B,C
E / 7 / Start
F / 2 / E

What is the duration of the critical path?
A.) 11
B.) 14
C.) 9
D.) 15

------------------------------
Hint: Use PDM to calculate.
------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC
The Project Management PrepCast™ - http://www.project-management-prepcast.com
The Project Management Podcast™ - http://www.project-management-podcast.com


ANSWER AND EXPLANATION:
The correct answer is B
Explanation: The critical path is EBD and the duration of the critical path of the data given is 14.
Reference: PMBOK Guide 4th Edition, page 138