EAC

26 views
Skip to first unread message

mad...@gmail.com

unread,
Apr 7, 2013, 4:37:16 AM4/7/13
to pmp-cert-onli...@googlegroups.com


We have 4 types of EAC formulas available, but am confused about when to use them

EAC =  BAC / CPI

EAC = ETC + AC

EAC = (BAC-EV) + AC

EAC = [BAC-EV / spi * cpi] + AC



I am having problem to decide how to calculate EAC? see this question:


As a project manager you realize that the initial budget cost, Budget at Completion (BAC) for your project is no longer viable. You need to develop a new Estimate At Completion (EAC) forecast assuming current variances would continue in the future. Which of the following formula should you use for calculating EAC? Here AC is the Actual Cost , EV is the Earned Value, PV is the Planned Value .




EAC = AC + ETC


EAC= AC+ (BAC - EV)


EAC = EV/PV


EAC = BAC/ cumulative CPI


Ramesh K R

unread,
Apr 8, 2013, 12:29:03 AM4/8/13
to pmp-cert-onli...@googlegroups.com
You should check Rita's book or Harwinder's excellent explanation at his site as below:

It is given in the question that current variance would continue in to future, so the correct formula would be BAC/CPI

Initially PV - 1000$ but now there is variance of 500 which resulted in spending 1500$. Also you expect this 1500 to be true value now on for spending.
So, thats what means - that variance continue in to future. In case you had the variance but you dont expect it to continue, i.e original estimate holds good now on, then the formula would be AC+(BAC-EV).

Regards
Ramesh PMP®


--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.
To unsubscribe from this group and stop receiving emails from it, send an email to pmp-cert-online-stu...@googlegroups.com.
To post to this group, send email to pmp-cert-onli...@googlegroups.com.
Visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.
For more options, visit https://groups.google.com/groups/opt_out.
 
 

Gurumoorthy Paulraj

unread,
Apr 7, 2013, 10:07:27 PM4/7/13
to pmp-cert-onli...@googlegroups.com
my answer is EAC = BAC/ cumulative CPI


Jawed Khan

unread,
Apr 8, 2013, 9:24:25 AM4/8/13
to pmp-cert-onli...@googlegroups.com
Hi
 
This is Jawed from Qaizen and below are the explanations to remove your confusion about calculating EAC
 
when the scenario is of calculating EAC at original budgeted rate you must use formula EAC= AC+ (BAC - EV)
and when the scenario says about calculating EAC at present or current rate than the formula will be  BAC / cumulative CPI 
 
Regards,
 
Jawed, PMP, ITIL, C2F
Skype:  jawed.khan87

Thanks and regards,
 
Jawed Khan, ITIL®,PMP® & C2F®
Vice President Certification Training
Qaizen Management & Consulting Services
TEAM:Together Everyone Achieves More..
Mob:+91-99874 83440 / 93242 06752
Skype: jawed.khan87/ Gtalk: jawed....@gmail.com
 
 


On Sun, Apr 7, 2013 at 2:07 PM, mad...@gmail.com <mad...@gmail.com> wrote:

Kanthan P

unread,
Apr 9, 2013, 2:57:45 AM4/9/13
to pmp-cert-onli...@googlegroups.com
Jawed, That's correct. If the project to continues at current variances EAC = BAC/CPI.
Reply all
Reply to author
Forward
0 new messages