Together with your team, you applied three-point estimation on a
Critical path which consists of two activities. The following duration
uncertainties are all calculated assuming a ±3sigma Confidence
interval. The duration uncertainty—defined as pessimistic minus
optimistic estimate—of the first activity is 18 days; the second
estimate has an uncertainty of 24 days. Applying the PERT formula for
paths, what is the duration uncertainty of the entire path? 94
o 21 days
o 30 days
o 42 days
o No statement is possible from the information given.
--
regards,
Meenakshi
--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.
To post to this group, send email to pmp-cert-onli...@googlegroups.com.
To unsubscribe from this group, send email to pmp-cert-online-stu...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.