Question on RISK

24 views
Skip to first unread message

Arash Zaree

unread,
Mar 1, 2012, 9:23:07 AM3/1/12
to pmp-cert-onli...@googlegroups.com
there is new project in organization, probability and impact matrix developed in which process?
1- PLAN RISK
2-IDENTIFY RISK
3-PERFORM QUANTITATIVE RISK ANALYSIS
4- PERFORM QUALITATIVE RISK ANALYSIS

Varun Paliwal

unread,
Mar 1, 2012, 10:57:53 AM3/1/12
to pmp-cert-onli...@googlegroups.com
I guess, the answer should be 'Perform Qualitative Risk Analysis'
 
Regards,
Varun


You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.
To view this discussion on the web visit https://groups.google.com/d/msg/pmp-cert-online-study-group/-/0173O9OHMC4J.
To post to this group, send email to pmp-cert-onli...@googlegroups.com.
To unsubscribe from this group, send email to pmp-cert-online-stu...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.

Sergey Vaskovsky

unread,
Mar 1, 2012, 5:24:24 PM3/1/12
to pmp-cert-onli...@googlegroups.com

I pick 4

--

Sagar

unread,
Mar 1, 2012, 11:16:59 PM3/1/12
to pmp-cert-onli...@googlegroups.com
The answwer is 
1. Plan Risk.
The probability and Impact matrices are developed during plan Risk management process and used during Perform Qualitative Risk analysis.
During Plan Risk management the existing org P&I matrices are taken and then they are tailored for project needs.

-Sagar,PMP

Imran Khan

unread,
Mar 1, 2012, 10:15:44 PM3/1/12
to pmp-cert-onli...@googlegroups.com

Answer is  4

--

Satish Singh

unread,
Mar 1, 2012, 11:43:34 PM3/1/12
to pmp-cert-onli...@googlegroups.com
Correct answer is "4- PERFORM QUALITATIVE RISK ANALYSIS"

#1 says "how"
#2 says "What"
#3 is further extension for analysis
#4 here we analyse the risk as a starting lvl 

Thanks
--
"Excellence is not a skill. it is an attitude"


Regards,
Satish.


Satish Singh

unread,
Mar 2, 2012, 1:13:48 AM3/2/12
to pmp-cert-onli...@googlegroups.com
Hello Sagar,

But during the planning , we don't have data to input in the matrices. 

Regards,
Satish.

--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.

To post to this group, send email to pmp-cert-onli...@googlegroups.com.
To unsubscribe from this group, send email to pmp-cert-online-stu...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.

Kuldeep Singh Solanki

unread,
Mar 2, 2012, 1:46:43 AM3/2/12
to pmp-cert-onli...@googlegroups.com
"Probability and impact matrix" developed during "Plan Risk Management". 

"Probability and impact matrix" is part of  Risk Management plan. Please refer to the page # 281 in PMBOK. 

Question is just asking when matrix is developed?  ANSWER will be 1- PLAN RISK

--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.

To post to this group, send email to pmp-cert-onli...@googlegroups.com.
To unsubscribe from this group, send email to pmp-cert-online-stu...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.



--
Please bear the formatting. Mail sent through mobile device.

Pranav Sheth

unread,
Mar 2, 2012, 2:20:53 AM3/2/12
to pmp-cert-onli...@googlegroups.com
Correct answer is D
Thanks and Best Regards,
Pranav Sheth,
PMP® .



setty sree

unread,
Mar 2, 2012, 2:28:28 AM3/2/12
to pmp-cert-onli...@googlegroups.com, Cornelius Fichtner

Hi Cornelius,
 
Can you kindly clear the doubt over here....
--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.

To post to this group, send email to pmp-cert-onli...@googlegroups.com.
To unsubscribe from this group, send email to pmp-cert-online-stu...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.



--
Thanks & Regards,
Sreelatha ITIL®,PMP®

Sri

unread,
Mar 2, 2012, 12:01:06 PM3/2/12
to pmp-cert-onli...@googlegroups.com
4- PERFORM QUALITATIVE RISK ANALYSIS 

First probability and impact and then rank them.. 

Arash Zaree

unread,
Mar 3, 2012, 2:33:48 AM3/3/12
to pmp-cert-onli...@googlegroups.com
Correct Answer will be 4. when there is LL from past project that matrix will be tailored in Planning but if there is not such matrix or its the first time it will be developed during perform QUALITATIVE risk analysis.

Nagarjuna

unread,
Mar 7, 2012, 7:10:11 AM3/7/12
to PMP Cert Online Study Group
1

Satish Singh

unread,
Mar 8, 2012, 2:28:05 AM3/8/12
to pmp-cert-onli...@googlegroups.com
Definition, and template for probability and impact matrix are put together in planning process. However, they are developed during the  QUALITATIVE RISK ANALYSIS.

thus, i think " PERFORM QUALITATIVE RISK ANALYSIS " is the correct answer. 
Anyone knows the source of this question and correct answer?
Thanks.

Regards,
Satish.


1
--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.
To post to this group, send email to pmp-cert-onli...@googlegroups.com.
To unsubscribe from this group, send email to pmp-cert-online-stu...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.




--
Reply all
Reply to author
Forward
0 new messages