My answer is b, since it is a new project it should have business case to gain support to have this project started.

On May 21, 2013, at 8:36 AM, gilbertgk <gilb...@gmail.com> wrote:

A PM is currently working on a project when the sponsor asked him to add a new requirement. He analyzed and found that the new requirement is not related to the current project and got  Sponsor's approval to initiate a new project for the same. What does the PM need for this?" and the typical answers would be:

a) Change control board approval
b) Business Case, Enterprise env factor and Org process assets 
c) both a and b
d) none


D because it should be treated as a new project ?

--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.
To unsubscribe from this group and stop receiving emails from it, send an email to pmp-cert-online-stu...@googlegroups.com.
To post to this group, send email to pmp-cert-onli...@googlegroups.com.
Visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.
For more options, visit https://groups.google.com/groups/opt_out.
 
 

Afzal khan

unread,
May 21, 2013, 1:41:51 AM5/21/13
to pmp-cert-onli...@googlegroups.com
I think  it should be B


On Tue, May 21, 2013 at 3:36 AM, gilbertgk <gilb...@gmail.com> wrote:

A PM is currently working on a project when the sponsor asked him to add a new requirement. He analyzed and found that the new requirement is not related to the current project and got  Sponsor's approval to initiate a new project for the same. What does the PM need for this?" and the typical answers would be:

a) Change control board approval
b) Business Case, Enterprise env factor and Org process assets 
c) both a and b
d) none


D because it should be treated as a new project ?

--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.
To unsubscribe from this group and stop receiving emails from it, send an email to pmp-cert-online-stu...@googlegroups.com.
To post to this group, send email to pmp-cert-onli...@googlegroups.com.
Visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.
For more options, visit https://groups.google.com/groups/opt_out.
 
 



--
-----------------------------------------------------------
Regards:

Mohd. Afzal Khan
Asst. Manager TCIL
Saudia Riyadh (KSA)
Mob: 966553800702
http://www.tcil-india.com/new/pics/TCILLOGO_(Blue)1.bmpIS/ISO 9001:2008
-----------------------------------------------------------

Gaurav Singh

unread,
May 21, 2013, 5:22:35 AM5/21/13
to pmp-cert-onli...@googlegroups.com
B is the best answer for new project to start as it contains business case.
> [image: http://www.tcil-india.com/new/pics/TCILLOGO_(Blue)1.bmp]*IS/ISO
> 9001:2008*
> -----------------------------------------------------------
>
> --
> You received this message because you are subscribed to the Google Groups
> "PMP Cert Online Study Group" group.
> To unsubscribe from this group and stop receiving emails from it, send an
> email to pmp-cert-online-stu...@googlegroups.com.
> To post to this group, send email to
> pmp-cert-onli...@googlegroups.com.
> Visit this group at
> http://groups.google.com/group/pmp-cert-online-study-group?hl=en.
> For more options, visit https://groups.google.com/groups/opt_out.
>
>
>


--
Best Regards,
Gaurav Singh

Padmavathi Varigonda

unread,
May 21, 2013, 7:44:57 AM5/21/13
to pmp-cert-onli...@googlegroups.com
Yes the answer is b.  Because to initiate a new project, PM need a business case, EEF and org process assets.

Deeksha Rastogi

unread,
May 21, 2013, 10:14:37 AM5/21/13
to pmp-cert-onli...@googlegroups.com
I'd go with B

Veeru

unread,
May 22, 2013, 3:16:49 AM5/22/13
to pmp-cert-onli...@googlegroups.com
"C" because the requirement should contain a business case etc. as well approval from the change control board(it may accept or reject the requirement).

Best Regards,
Veera

Ramandeep Chahal

unread,
May 23, 2013, 12:44:53 AM5/23/13
to pmp-cert-onli...@googlegroups.com
For me there is no trick in this question its pretty straight forward... start reading from "Sponsor's approval to initiate a new project for the same. What does the PM need for this?" and the typical answers would be:"

Answer should be B

Regards,
Ramandeep S. Chahal

Ramandeep Chahal

unread,
May 25, 2013, 1:39:40 PM5/25/13
to pmp-cert-onli...@googlegroups.com
What's the correct answer?

Regards,
Ramandeep S. Chahal

gilbert khayat

unread,
May 26, 2013, 8:55:49 AM5/26/13
to pmp-cert-onli...@googlegroups.com
I dont have the correct answer and it seems that there are a lot of different answers. can anyone confirm whats the most likely answer?
Gilbert Khayat

Ramandeep Chahal

unread,
May 31, 2013, 1:11:40 AM5/31/13
to pmp-cert-onli...@googlegroups.com
A is definitely not the answer for this question hence C (as it include A as a choice) because in order to start a new Project or Phase we do not need an approval from the Change control board. We definitely need the business case in order to see if the project is worth doing i.e Business case (and obviously the EEF and OPAs), so I will stick with B as my answer.

gilbert khayat

unread,
May 31, 2013, 8:38:31 AM5/31/13
to pmp-cert-onli...@googlegroups.com
I agree with Ramandeep. by the way I am happy that you are back..:)

Arvind

unread,
Jun 4, 2013, 10:34:43 PM6/4/13
to pmp-cert-onli...@googlegroups.com
Answer is B


On Mon, Jun 3, 2013 at 9:52 AM, Rajeev Polepalli <rajeev.p...@gmail.com> wrote:
Answer: B

sinha.v...@gmail.com

unread,
Jun 5, 2013, 12:03:01 AM6/5/13
to pmp-cert-onli...@googlegroups.com
B
Please ignore typos @ Blackberry

From: Arvind <hsar...@gmail.com>
Date: Tue, 4 Jun 2013 22:34:43 -0400
Subject: Re: very tricky question

Deeksha Rastogi

unread,
Jun 12, 2013, 4:34:43 AM6/12/13
to pmp-cert-onli...@googlegroups.com
I'd go with B too, because since it is a new project, he will need the Business Case, Enterprise env factor and Org process assets 

Nilesh Amrutkar

unread,
Jun 12, 2013, 10:57:05 PM6/12/13
to pmp-cert-onli...@googlegroups.com
answer is B. since its new requirement and new project there is no
question about change control board approval.

On 6/12/13, Deeksha Rastogi <deekshaank...@gmail.com> wrote:
> I'd go with B too, because since it is a new project, he will need the
> Business
> Case, Enterprise env factor and Org process assets
>
>
> On Wed, Jun 5, 2013 at 9:33 AM, <sinha.v...@gmail.com> wrote:
>
>> **
>> B
>> Please ignore typos @ Blackberry
>> ------------------------------
>> *From: * Arvind <hsar...@gmail.com>
>> *Sender: * pmp-cert-onli...@googlegroups.com
>> *Date: *Tue, 4 Jun 2013 22:34:43 -0400
>> *To: *<pmp-cert-onli...@googlegroups.com>
>> *ReplyTo: * pmp-cert-onli...@googlegroups.com
>> *Subject: *Re: very tricky question

Joyson

unread,
Jun 13, 2013, 1:47:02 AM6/13/13
to pmp-cert-onli...@googlegroups.com

The answer should be "B" as this is a new project

Afzal khan

unread,
Jun 15, 2013, 5:41:18 PM6/15/13
to pmp-cert-onli...@googlegroups.com
It is true that  it should be treated as a new project and for the New Project you need the Project Charter . and option B Business Case, Enterprise env factor and Org process assets are input to the Develop project Charter so the correct Answer is B
i hope it answer the question.
regards 
Afzal

Sandra Strech

unread,
Aug 13, 2014, 10:00:27 PM8/13/14
to pmp-cert-onli...@googlegroups.com
Given the limitations listed, B because the Charter for the new project would need to Business Case, EEFs and OPAs.  The question is tricking you because B is part of the Charter and the critical need is the Charter.

Frances M J Tessler

unread,
Aug 20, 2014, 10:22:39 AM8/20/14
to pmp-cert-onli...@googlegroups.com, gilb...@gmail.com
In the first sentence the sponsor had already review the request which was Perform Integrated Change Control. Once the sponsor decided it was a new project then B would be what was needed. The business case, EEF & OPA would have initially been part of the change request that he would have taken to the Sponsor for approval to start a new project. So B is the answer.