A PM is currently working on a project when the sponsor asked him to add a new requirement. He analyzed and found that the new requirement is not related to the current project and got Sponsor's approval to initiate a new project for the same. What does the PM need for this?" and the typical answers would be:
a) Change control board approval
b) Business Case, Enterprise env factor and Org process assets
c) both a and b
d) none
D because it should be treated as a new project ?
--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.
To unsubscribe from this group and stop receiving emails from it, send an email to pmp-cert-online-stu...@googlegroups.com.
To post to this group, send email to pmp-cert-onli...@googlegroups.com.
Visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.
For more options, visit https://groups.google.com/groups/opt_out.
A PM is currently working on a project when the sponsor asked him to add a new requirement. He analyzed and found that the new requirement is not related to the current project and got Sponsor's approval to initiate a new project for the same. What does the PM need for this?" and the typical answers would be:
a) Change control board approval
b) Business Case, Enterprise env factor and Org process assets
c) both a and b
d) none
D because it should be treated as a new project ?
--
You received this message because you are subscribed to the Google Groups "PMP Cert Online Study Group" group.
To unsubscribe from this group and stop receiving emails from it, send an email to pmp-cert-online-stu...@googlegroups.com.
To post to this group, send email to pmp-cert-onli...@googlegroups.com.
Visit this group at http://groups.google.com/group/pmp-cert-online-study-group?hl=en.
For more options, visit https://groups.google.com/groups/opt_out.

IS/ISO 9001:2008Regards,
Ramandeep S. Chahal
Regards,
Ramandeep S. Chahal
The answer should be "B" as this is a new project