Folks,
I'll be taking the PMP exam this Friday, and I wanted to pick everyones brain to see what items I should have on my braindump sheet. Thus far I have:
1) The entire process chart (knowledge areas, process groups, and processes per knowledge area)
2) Earned Value Formulas (ETC, EAC, VAC, BAC, PTA, CV, SV, SPI, CPI, (MISC Comm channel formula, EAD, SD, Variance)
3) 1, 2, 3, and 6 Sigma percentages
4) Order of magnitude ranges
I know the quality theories by heart (Juran, Deming, Crosby, Herzberg, McClelland, etc..).
Other thoughts?
Milan