Qs. Your project work has generally been finished and you want to commence a solid closing process for the project. What must have been attained to begin this process?
A. The deliverables of the project must have been accepted.
B. The Organizational process assets must have been updated.
C. The final product, service or result transition must have been finished.
D. Lessons learned must have been organized into a data base.
If you know the answer, reply to your group with reason
or follow below instructions for the correct answer
- Visit
http://pmbootcamp.org
- Click on FAQ
- Search below keyword
- PMBC5021
Good luck for PMP Exam.
Regards,
PM Guru
pmg...@pmbootcamp.org