PMP - Qs: Your project work has generally been finished and...

26 views
Skip to first unread message

PMBootCamp.Org

unread,
Oct 29, 2012, 7:50:06 PM10/29/12
to pmi-sr...@googlegroups.com
PMP(r) Daily Wisdom from http://pmbootcamp.org
Ranked #1 by several groups, 2400+ PMP Questions
PMBOK Latest Edition & thoroughly tested by PMP's
Someone said 'It is most closest to PMP(c) Exam'
7 students also said 'Hope I had found it earlier'
Read PMBOK(c) in 2hrs by reading 310 points from
our Secret Cheat Sheet + Chapterwise for PMP exam
--------------------------------------------------


Qs. Your project work has generally been finished and you want to commence a solid closing process for the project. What must have been attained to begin this process?
A. The deliverables of the project must have been accepted.
B. The Organizational process assets must have been updated.
C. The final product, service or result transition must have been finished.
D. Lessons learned must have been organized into a data base.

If you know the answer, reply to your group with reason
or follow below instructions for the correct answer
- Visit http://pmbootcamp.org
- Click on FAQ
- Search below keyword
- PMBC5021
Good luck for PMP Exam.

Regards,
PM Guru
pmg...@pmbootcamp.org

Reply all
Reply to author
Forward
0 new messages