Limiting WIP ... too difficult?

36 views
Skip to first unread message

Jim Benson

unread,
Feb 15, 2014, 1:34:59 PM2/15/14
to persona...@googlegroups.com
There are two rules for Personal Kanban. - Visualize Work and Limit Work In Progress.

I've found recently that all PK practitioners visualize work, but few seem to be limiting their WIP. 

I won't be hurt, but I need to know:

If you aren't limiting WIP ... why? 
--
Jim Benson
Collaborative Management
Modus Cooperandi: Performance Through Collaboration 
Personal Kanban: Effective, Lightweight Personal and Small Team Organization
Skype: ourfounder
Phone US +1.206.383.6088
Add Me on Linked In

Paul Klipp

unread,
Feb 15, 2014, 2:18:30 PM2/15/14
to persona...@googlegroups.com
You think I limit my WIP too much, but years later, a WIP limit of one still works for me.

Paul

____________________
Paul Klipp, KCP, CSP
Lean-Agile Coach
www.paulklipp.com

Q: Why is this email five sentences or less?
A: http://five.sentenc.es


--
-- You received this message because you are subscribed to the Google Groups Personal Kanban Community of Practice group. To post to this group, send email to persona...@googlegroups.com. To unsubscribe from this group, send email to personalkanba...@googlegroups.com. For more options, visit this group at https://groups.google.com/d/forum/personalkanban?hl=en
---
You received this message because you are subscribed to the Google Groups "Personal Kanban Community of Practice" group.
To unsubscribe from this group and stop receiving emails from it, send an email to personalkanba...@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.

Agustin Villena

unread,
Feb 15, 2014, 5:06:48 PM2/15/14
to persona...@googlegroups.com

I try hard to follow the "one small goal at a time" rule. Problems arise when the work-in-progress item us blocked,  usually by dependences on 3rd parties. Therefore focusing on another item "seems" to be the obvious thing to do. It is still not clear to me that this is always wrong.

Limiting Wip IMHO is like starting a diet. Requires much discipline and a focus on the whole workflow.

In Kanban (at team  level) the natural way to limit WIP is to prioritize the same amount of work than you archieved the last week (like in Scrum,  or XP) . I have some successful experiences coaching personal kanban and appying the same principle, but the above issue still remains

Regards
Agustin Villena

--