Sorry for the delay in responding to the comment:  

“Please let us know what steps are being taken to assure that all needed water/sewer work is done when the street is dug up for the reconstruction”

 

The project team is coordinating with PWSA regarding the water line and storm sewers on Penn Avenue.  The project team plans to discuss this in more detail at the January 12, 2012 meeting at St Lawrence O’Toole at 6:00 PM (refreshments will be served).  

 

Thanks,

 

John

 

cell: 412-973-9285

 

john j. CLARK & ASSOCIATES, Inc.

 

WWW.CLARKSERVICES.NET

  

 

image001.jpg

William Cornell

unread,
Jan 4, 2012, 2:32:41 PM1/4/12
to penna...@googlegroups.com
Dear John,

Thanks for getting back to us.  I am the president of the BGC Board, and we have grave concerns about the possibility of the Penn Avenue reconstruction occurring with the possibility of the current, horrid water/sewer system left unattended.  It is very good news that there is a team coordinating with PWSA.  Many of us will be at the meeting on the 12th.  Needless to say, there is great interest and great concern.

Bill
-- 
You received this message because you are subscribed to the Google Groups "Penn Ave Community" group.
To post to this group, send email to penna...@googlegroups.com.
To unsubscribe from this group, send email to pennavepgh+...@googlegroups.com.
For more options, visit this group at http://groups.google.com/group/pennavepgh?hl=en.

Reply all
Reply to author
Forward
0 new messages