Parsvnath Developers Ghaziabad – Cheating Cheating Cheating Cheating

438 views
Skip to first unread message

djain128

unread,
Aug 2, 2011, 5:10:28 AM8/2/11
to Parsvnath-La-Tropicana-flatOwners-Grievences
Parsvnath Developers Ghaziabad – Cheating Cheating Cheating Cheating

Parsvnath Developers Ghaziabad – Cheating Cheating Cheating
Cheating


Parsvnath three projects - Exotica, Sterling, Regalia


All projects tentative possession date was 3 years from booking
opening started in 2006/2007. planned to give possession in 2009/2010.
Will not give possession in all three project in next 10-20 years.

Had given penalty clause in agreement and said it is to show that
we have no intention to make delay in possession. Now planning to
utilise penalty clause to make own profits by giving penalty payment
2%-3% per year (per month 5 per square feet) of payment received by
him, for next 10-20 years, while people are paying home loan interest
10%

Submit Complaint.. Submit Complaint.. IP
09-20-2009 12:10 PM #2
Unregistered Guest
Default Parsvnath Developers Ghaziabad

Quote Originally Posted by Unregistered View Post
Parsvnath Developers Ghaziabad

Parsvnath three projects - Exotica, Sterling, Regalia
Above statement has one correction. It may not delay by 10-20
years because Company has good reputation in market and good image in
real estate industry.

But all these projects are supposed to be delayed by few years.
Because all these three projects had no major progress in last one
year. Chances are very less that these will be delivered for
possession within promised time schedule 2009/2010.

Submit Complaint.. Submit Complaint.. IP
09-20-2009 05:39 PM #3
Unregistered Guest
Default Parsvnath Developers Ghaziabad

Quote Originally Posted by Unregistered View Post
Parsvnath Developers Ghaziabad – Cheating Cheating Cheating
Cheating


Parsvnath three projects - Exotica, Sterling, Regalia


All projects tentative possession date was 3 years from booking
opening started in 2006/2007. planned to give possession in 2009/2010.
Will not give possession in all three project in next 10-20 years.

Had given penalty clause in agreement and said it is to show that
we have no intention to make delay in possession. Now planning to
utilise penalty clause to make own profits by giving penalty payment
2%-3% per year (per month 5 per square feet) of payment received by
him, for next 10-20 years, while people are paying home loan interest
10%

It may not delay by 10-20 years, because Company has good
reputation in market and good image in real estate industry.

But all these projects are supposed to be delayed by few years.
Because all these three projects had no major progress in last one
year. Chances are very less that these will be delivered for
possession with promised time schedule 2009/2010.

Submit Complaint.. Submit Complaint.. IP
10-27-2009 02:50 PM #4
Unregistered Guest
Default

Quote Originally Posted by Unregistered View Post
Parsvnath Developers Ghaziabad – Cheating Cheating Cheating
Cheating


Parsvnath three projects - Exotica, Sterling, Regalia


All projects tentative possession date was 3 years from booking
opening started in 2006/2007. planned to give possession in 2009/2010.
Will not give possession in all three project in next 10-20 years.

Had given penalty clause in agreement and said it is to show that
we have no intention to make delay in possession. Now planning to
utilise penalty clause to make own profits by giving penalty payment
2%-3% per year (per month 5 per square feet) of payment received by
him, for next 10-20 years, while people are paying home loan interest
10%
Have you talked to their employees on the site they are all
clueless. Recently they put few laborers on the work but once Diwali
is over the laborer are gone ( Gimmick to attarct clients) . They need
to be brought to books for cheating hundereds of people.

Submit Complaint.. Submit Complaint.. IP
11-09-2009 02:58 PM #5
atul...@yahoo.com
atul...@yahoo.com is offline Junior Member atul...@yahoo.com is on a
distinguished road

Join Date
Nov 2009
Posts
1

Default Parsavnath Exotica at Ghaziabad

I had booked at 3 bedroom flat at exotica in May 2008. It was
assured that the development of the project is in full swing and
possession in 3 years.
I had opted for down payment and applied for loan.
i made all the payemnts and got home loan at floating rate of
interest of 11.5% from DHFL.
however, as per the current situation it appears that project is
bound to be delayed by many years since there is absolutely no
construction going on. the site construction is almost same as it was
an year back at the time of payment.
i am incurring dual loss, 11.5 % interest on my home loan and
further interest loss of all my savings that went as downpayment.
Parsvanth keeps on declaring and investing on new projects but
already started project seems to be in doldrums.
they seem to be cheating their customers. every time you try to
contact Parsavnath office, they have nothing more to often except
false assurances

Submit Complaint.. Submit Complaint.. IP
11-10-2009 11:39 PM #6
Unregistered Guest
Default we are also cheated by parsvnath

I had booked a 3 bedroom flat at Parsvnath exotica but the project
is not taking shape for many years now. am living on rent and paying
home loan.In this long process am cheated as have made down payment to
them.
we request the buyers who feel cheated to form a group with me and
a forum and get against the builders for cheating charges
in one such case against DLF and Unitech the builders have
returned the money with interest when the buyers have moved against
them in a group for cheating charges
kindly call me on my number as am in the process of forming a
group and taking it seriously
my number is 9871226871

Submit Complaint.. Submit Complaint.. IP
11-11-2009 01:48 PM #7
adv.om
adv.om is offline Senior Member adv.om is on a distinguished road

Join Date
Nov 2009
Posts
101

Default

kindly form a group and write to the builder and also warn him of
legal action and it is better that after froming a group you file a
case in consumer forum it will work faster accoring to me sir

Submit Complaint.. Submit Complaint.. IP
11-23-2009 10:21 AM #8
Unregistered Guest
Thumbs up Parsavnath Exotica at Ghaziabad

I welcome the idea of formation of group of cheated buyers. we
want to raise a strong voice against the builders.
Please register yourself to raise voice by registering yourself to
this blog.my number is 09334201195

Submit Complaint.. Submit Complaint.. IP
12-01-2009 03:47 PM #9
Unregistered Guest
Default parsvna...@gmail.com

for all complaints suggestions against parsvnath builders please
mail us at

parsvna...@gmail.com

or call us at 9871226871

Submit Complaint.. Submit Complaint.. IP
12-25-2009 01:57 PM #10
Unregistered Guest
Angry Cheated by Parsavnath Sterling at Ghaziabad

I have booked a flat in Sterling Parsvnath Gzb, No progress has
been seeing since 2008,
I visited Parsvnath corporate office in CP Delhi, number of times
but end up with false statement/assurance, per recent conversation
with corporate office “There is a fund crunch with the company and in
talk with some investment company to finance for running project”.

I strongly welcome this idea to raise voice against Parsvnath,
let’s come up with a plan to move further.

Contact: tawar...@gmail.com

Submit Complaint.. Submit Complaint.. IP
01-03-2010 09:35 PM #11
payal_sarin
payal_sarin is offline Junior Member payal_sarin is on a distinguished
road

Join Date
Jan 2010
Posts
1

Default parsvnath dvelopers ghaziabad

dear sir
i also bought three bedroom flat in parsvnath regalia in feb 2008
on full down payment on assurance that i will get the possession in
june 2009.
Nothing is happening on the site for the last one year.
When i called them at there corporate office , i was told that
flats will be ready by june 2010, still no construction is going on
the site.
I am very worried if they will complete the project or not,
because i have bought a flat on loan and i m paying interest at the
rate of 11.5%.
I am keen to join any forum against parsvnath developers and ready
to take legal action against them if other members of the group are
willing to fight legal bettle against cheaters.

thanks & regards

Submit Complaint.. Submit Complaint.. IP
01-04-2010 03:57 PM #12
Unregistered Guest
Angry D R Gaur Projects Pvt Limited Delhi

Subject: Refund for Surrender of Provisional Regis
Ref. Application dated 01/04/07
Customer Code No M-39/1001
Receipt No 0000001001 Dated 21/04/07
Dear Sir,

I wish to submit following facts:
1. I had booked for a studio apartment in the above mentioned
builders River mount valley Manali project vide above mentioned
application and have paid a sum of Rs. 1,40,000/- (Rupees One lakh
forty thousand only) which has been duly acknowledged by you vide
above referred receipt.
2. A notice regarding land of the project appeared in the news
paper on 18th of Feb 2008 regarding counter claims by the owner of the
land.
3. On contacting your office, I was informed verbally that the
project is abandoned due to non approval.
4. I immediately filed an application for refund on 20th of Feb.
2008
5. All the requisite documents were submitted at the time of
applying for surrender.
6. I was asked by builders office to come and collect a cheque for
the principal amount plus interest after fifteen days.
7. Even after repeatedly informing the builders staff that I am
stationed at Alwar for my office, I was harassed, to travel to his
Ashok Hotel office & Gurgaon office again & again for payments.
8.The cheque no 291300 of Union Bank Of India, SSI Finance branch,
Gurgaon-- for Rs 1,40,000/- (Rupees One lakh forty thousand only)
dated 30/09/08 was handed over to my representative after a number of
visits to builders office.
9. The cheque when presented in the bank on 3rd of Oct 2008 was
not honoured and I was informed by my bank that there were
insufficient funds in the bank. I received the dishonored cheque on
8th of Oct 2008.
14. Mr. Naresh Gaur (MD)is not available in office and he never
bothers to answer his mobile no 09811125512. No other person in his
office at ashoka hotel and Gurgaon office assumes the responsibility
of informing the status regarding the refund.
15. Through this forum I would like to gather momentum against
this fraudulent group that is cheating service class investors of its
hard earned money and I solicit other customers who may have been
cheated by this group to come together to strengthen our voice against
their fradulent activities and malpractices and put up a case against
these cheats in the honorable courts of India for justice due to us.

I hope to get a positive result by lodging my complaint on the
forum.

Thanking you,
Yours truly,


Signature
Full name: Sanjay Bhatnagar R/O: 107, Sector – 15- Faridabad
Mobile 09982687034

Submit Complaint.. Submit Complaint.. IP
01-04-2010 04:07 PM #13
admin
admin is offline Administrator admin has disabled reputation

Join Date
Sep 2008
Posts
2,982

Default

Hello Sanjay Bhatnagar,

This is a civil case, and for that you need to consult to any good
lawyer.

Regards,
Admin,

** PMs asking me for support will be deleted unless I've asked you
to PM me with additional details **

Submit Complaint.. Submit Complaint.. IP
01-05-2010 09:47 PM #14
parsvna...@gmail.com Guest
Default parsvnath complaint

for all complaints suggestions against parsvnath builders please
mail us at

parsvna...@gmail.com

or call us at 9871226871

Submit Complaint.. Submit Complaint.. IP
01-26-2010 01:32 PM #15
Rinesh Guest
Default We are also fooled by Parvsnath

My old parents invested their retirement money into their Bhiwadi
city centre project and we are nowhere now. Their people are just
sitting over our money. The interest on our money already paid to you
is accumulating and we are not getting any correspondence from their
office.

Whenever we call their official over mobile 9818583626 he is least
concerned about our problem and has only one answer - that the work
has not started on the project. We even travelled to the site in
Bhiwadi couple of months back and the official sitting there assured
us that the work would start within a week, but that week never
arrived. It seems they have imparted fantastic training to their
people on "how to fool people". For the huge investment made we need
at least communication from them that the project is cancelled /
delayed etc. However, none has come from their side and it seems these
people have taken us for grant

PDL

unread,
Jan 13, 2012, 3:44:48 AM1/13/12
to parsvnath-la-tropicana...@googlegroups.com

Dear Customers,

Various blogs have appeared without verifying site realities. For actual construction status of this FDI backed project, please visit:

http://www.parsvnath.com/residential/ghaziabad/parsvnath-exotica/site-photographs.asp?pr=exotica

Parsvnath Exotica, Ghaziabad is a unique Freehold project backed by FDI offering various options of 3/4/5 bhk Super luxurious Condominiums at value for money price. It is rated as one of the best projects in and around that region.

A visit to our Site & Sample house would illustrate the claim.

We welcome all customers to personally get in touch for all the queries and updates at : 9650433711 / 9717333926

Regards

PDL

Vin Ssaini

unread,
Aug 15, 2015, 2:40:32 AM8/15/15
to Parsvnath-La-Tropicana-flatOwners-Grievences
Dear PDL,

I have a flat in Parsvnath Sterling Ghaziabad. Can you please update as when you are expected to complete this project and hand it over to your customers?
Also explain why you have extended the allocated area, with out askiing/information and now asking to pay extra money, which is against the law?

Thank You,
Kulvinder S Saini
9811900446