Update-
1. We were not allowed to visit the site. No one was aware of our visit. Infact we talked with marketing head and as per him there is no way we can get access to construction site. As per our observation from outside on an average plaster has been completed upto 6 and 7 floor. Everyone's view is completion of entire project in a year time is little unrealistic.
2. We also discuss about interest issues. Most of us received the letter/mail from builder by saying earlier letter is null and void. But we learnt builder is planning to get the interest at the time of possession. So we'll have no time to fight.
Action items:
1. Formed a formal/legal group and meet with senior management in paramount and discuss on above issue. If builder is agree on issuing a letter with 0 interest then fine otherwise we need to file the case in consumer court. Builder is playing very smart he'll ask for interest at the time of possession and we all would be end up by paying that amount. Now we need to take proactive steps instead of reactive.
Now we need some legal opinion on taking things further..
Key mile stones :
12/01/2013 - Meet the builder under the formal/legal group and have an agreement.
19/01/2013 - Send the formal notice to builder on the point where we are having disagreement.
25/01/2013 - file a complaint in consumer forum by the group
Need everyone's help to achieve above milestone. We all need to remember one thing, it's a time to fight for ourselves.
As a first step We can pick items from the post Intent to form "Flat Owners Association" and its Agenda
http://tinyurl.com/ParamountFloravilleAgendaDraft
Wish you & your family a very happy & prosperous new year !
--
--
--
| Dear All, I to agree with Kunal's observation because delay of poccession is some thing we all cannot afford. The issue of no being able to evaluate the progress of the project is alarming. I was informed last year than in 2012 we would be able to see the interior work of our apartment --- On Thu, 1/3/13, Varun Thukral <varu...@gmail.com> wrote: |
|
|
An official spokesperson said the supplementary order passed by the CCI under Section 27 of the Competition Act, 2002, modifies the agreement entered into between DLF and apartment allottees and relates to the order of the Competition Appellate Tribunal of March 29, 2012.
The Tribunal had directed the Commission to pass an order specifying the extent and manner in which the terms and conditions of the apartment buyer's agreement needed to be modified.
The Commission in its order after considering the modified terms of the Apartment Buyers agreement submitted by both the parties, modified the terms of the agreement in a manner which it considers fair and reasonable and takes into account the interest of both the parties, the spokesperson said.
The Commission had, in its earlier August 12, 2011, order held that DLF Ltd was a dominant enterprise which had "violated the provisions of Section 4 of the Competition Act 2002 by entering into an agreement with apartment allottees that was one sided, abusive and unfair to the allottees."
Accordingly, the agreement had been amended such that the "abusive and unfair conditions present in the original one-sided agreement have been removed."
The Commission in its order also considered the relevant provisions of the laws applicable to the development of group housing projects in Haryana, particularly the mandatory requirements which must be followed by every developer/builder, but which were not followed by DLF Ltd in this case.
The order of the Commission has been passed in case number 19 of 2010.
--
--
Even an individual can file a case against the builder.
Regards
Ankur Gupta
|
|
I think we should start preparing ourself to file a case before the consumer forum, since, formation of an association or not, builder is not going to listen to us now, otherwise, he owuld not have issued the revised interest calculations.
Regards
Ankur |
|
|
|
|
Ankur, it would be great help if you can help/guide us in preparing our case.
I think one point would be common for all, why interest component not appeared in subsequent demand letter. We would have learnt our lesson from the first installment. Builder intention was malicious and they allow interest component to grow over a period of more than 2 yrs.
I think, it was good to meet Mr. Vijay.He mentioned that we can only file an individual case in consumer court. A group or an association can NOT file a case in consumer court.We also verified if we have a valid points to go for consumer court1. Some of the earlier receipts from builder does not have Service Tax mentioned. All of a sudden, one of the payment against the demand letter was adjusted against past outstanding service tax (sometime in 2011) - for which we never received a demand letter. This shows that builder is not following legal practice in raising the right demand letter and taking payments under consideration. This causes imbalance of accounts on the buyer part - causing outstanding and chargeable for interest.2. (for whom the revised interest demand letter received) - Again, legal practice is not followed by intimating buyers about any outstanding/overdue interest payment in every demand letter raised by them.3. (for whom the revised interest demand letter received OR not received) - Receiving letter of interest and pulling-off in December-2012 was mental agony.4. No status on delivery of the project to buyers.---------As per my understanding, forming an association would not really impact on the results that we are looking at. As course of action would be really from going to consumer court - individually. Bulk cases in consumer court against the builder for a specific project is considered as a big deal.I'm suggesting to meet this Sunday, Jan-27th, at 11:00 am at Star City Mall, Opposite Mayur Vihar Phase -1 Extension metro station for further discussion and immediate next steps.Regards,Manish
--
| must also add that there is no access to the project for the buyer/owner of the apartment --- On Wed, 1/23/13, Manish Panjwani <panj...@gmail.com> wrote: |
|
--