This meeting was focused on the work being done by individual teams:

CS Team:
Preparing movement and vision modules for next pool test. Also organizing a learning night:
Thursday, February 27th, at 4:30pm in Sloan 9

ME Team: 
Formally presented submarine design and is receiving parts this week. They will be machining the various components over the next few weeks.

EE Team:
Finalized PCB designs allow ordering all necessary components this week. The process of porting the micro controller code into sub processes for use in the various micro controllers on the new submarine has begun.

Congratulations to our team members of the week! Please follow Robosub on Twitter for more consistent updates, as well as liking our Facebook page!
https://twitter.com/RoboSubPalouse