Update for 20/6/12

4 views
Skip to first unread message

Christopher Fraser

unread,
Jun 20, 2012, 1:21:55 PM6/20/12
to open-...@googlegroups.com
* Camp details page:

http://openeland.org/2012/06/camp-details/

Waiting on Spanish translation before making public.

* Camp registration page:

http://openeland.org/2012/06/camp-registration-form/

* Humanure toilet structure up. Needs doors and painting etc but close:

http://openeland.org/wp-content/uploads/2012/06/toilet.jpg

Once we have a bugs worked out I'll publish the drawings in case
anyone wants to reuse the design.

* New shade structure up and cooking/washing area built. Canopy has
had tensioners installed since this photo:

http://openeland.org/wp-content/uploads/2012/06/shade.jpg

* Purchased materials for solar hot water shower system

* Found local source of cane. Henrik looking at building a prototype dome.

* CEB press is more or less complete. Compression action is OK but
eject isn't. Problem seems to be the fit and alignment of guide tubes
needs to be much more accurate than I constructed. May need to remake
piston guide tubes.

http://openeland.org/wp-content/uploads/2012/06/press31.jpg

* Now managing to get 400L of water at a time, which should be enough
for camp.

* Bank account apparently now working.

* Will be publishing some fundraising details soon.