My comments to the 5% metering accuracy draft follow.
We have real heartache with only one test. Test #2, Load Performance
would be difficult, if not impossible to pass. Some laboratory meters
would even have some difficulty meeting the requirements at the 10%
power level. Test #5, Effect of Internal Heating is a bit unclear.
Test#2, Load Performance
Essentially, as written, the test requires a built-in meter with a 0.5%
full scale accuracy. I would like to offer a prudent and reasonable
solution. There are two parts to this:
1. Run the test as described. Apply the Weighted Accuracy formula as
was described in the marked out equation 4-2, except delete the first
term, as we do not do efficiency tests at the 5% power level. Apply the
CEC weighting factors of Power/Weight; 10%/4%, 20%/5%, 30%/12%, 50%/21%,
75%/53%, 100%/5%. Then, change the Pass/Fail criteria to read "The
weighted accuracy as calculated by formula 4-2 must be in the range of
+/-5%."
2. Our intent is to run the meter tests in conjunction with other tests
which are already being performed, as much as possible. We do not
perform the tests in rows D and E of table 4-1. We should, however,
verify the meter accuracy at ac voltages other than nominal. I would
suggest that we grey out the boxes in 10%, 20%, 30%, 50%, and 75% in
rows D, change the Vdc to Vnom, and delete row E. The test to verify
meter accuracy at low and high line voltage shall be performed at 100%
power only. So, this test essentially integrates Test #3, Effect of
Variation of Voltage.
Test #5, Effect of Internal Heating
I would propose that we perform this test during the CEC maximum
continuous power test. This involves 150 minutes of maximum power at
40c. Pass/Fail would be that the meter accuracy is within 5% as defined
by equation 4.1 at the end of the 150 minute test. We might also
consider a maximum deviation from the result of the 100% power test in
Test #2 of 2.5%.
Test #7, Independence of Elements
Let's clarify that a split-phase system is not considered multi-phase.
Grid Interactive inverters should have no problem with this test, as
they are required to cease exportation of power upon loss of phase.
Maybe a definition is section 2.1. "Multi-phase units: an inverter
which exports power on more than 2 conductors."
Test #11, Effect of Variation of Ambient Temperature
Seems like we should be able to combine Test #5, Effect of Internal
Heating and Test #11, Effect of Variation of Ambient Temperature into
one test. By starting the test at the lowest temperature, the total
test time is less. Also, if we change the power levels to 50% and 100%
we can cut this test time in half, and allow integration with the
standard UL1741, section 43 temperature test. In fact, Test #3, Effect
of Variation of Voltage can be run at this time, as we already run the
four corners of DC and ac voltage combinations during the temperature
test. If minimum storage and operating temperatures are the same, Test
#17, Effect of Operating Temperature can be run prior to running Test
#11, but with the same equipment setup.
Comments welcome!
See Ya!
Marv
Enphase Energy
707 763-4784 x7016
Chaset, Nicolas L. wrote:
> 5% metering accuracy group-
>
> First let me extend my thanks to to Matt Lafferty and Pete Baumstark for
> all the work they have both done to move this standard forward. As
> things currently stand, we are very close to having a completed testing
> specification and there is now one last opportunity to provide comment
> before the specification is finalized. All interested parties should
> review the draft document that Matt Lafferty sent out last week and
> provide comment to Pete Baumstark (
pete.ba...@kema.com
> <mailto:
pete.ba...@kema.com>) no later than one week from today
> (March 25, 2009). The CPUC and the California Solar Initiative Program
> Administrators may hold a future workshop to discuss implementation of
> the 5% metering accuracy standard, but not timeline has be developed for
> that as yet.
>
> Thank you all for your collaboration.
>
>
> Nicolas Chaset
> California Solar Initiative
> California Public Utilities Commission
>
415-703-1184
>
n...@cpuc.ca.gov <mailto:
n...@cpuc.ca.gov>
>
> >