Project progress report

47 views
Skip to first unread message

Lokesh Kumar

unread,
Jun 13, 2013, 1:07:38 AM6/13/13
to nri-city-yamu...@googlegroups.com
Hi,
 
If any one have idea about current progress on this project please update here.
 
Thanks,

Lokesh Kumar

unread,
Jul 15, 2013, 5:25:13 AM7/15/13
to nri-city-yamu...@googlegroups.com
Hi All,
 
I was there on July 13, 2013 below are the updates releated to progress on this project.
 
1. builder placed 4 transfarmer for electricity purpose.
2. I saw progress in road construction work. Solid concreate are there on all road as per my observation they must take atleast 4-5 months for road completion work.
 
As per my observation we can saw good changes in next 4-5 months. I had discussion with SDS staff and as  per our discussion SDS is planning for group housing lunch near to end of this year.
 
I also do discussion on current market price and its min 22,000/- sq yard and there are good chance of appriciation after road completion work.
 
 
Thanks,
 

Dinesh Kumar

unread,
Nov 11, 2013, 1:44:10 AM11/11/13
to nri-city-yamu...@googlegroups.com
Hi,

Regarding NRI Residency got the final demand letter and they promise to give possession in December 2013.

Not sure where they will give late possession money as project is already delay 1 year.

Thanks,
Dinesh Jagnere 

Lokesh Kumar

unread,
Nov 11, 2013, 7:13:25 AM11/11/13
to nri-city-yamu...@googlegroups.com
Thanks for update all of us. I think they demand you for road completion work. It better if you update the group with more information.

Till Now I don't receive any demand letter from SDS hope its in way.