Dear Patron, Greetings from Nitesh Estates!! EXPECT MORE - the Nitesh discipline, is the inspiration behind our work ethic and drives forward our innovative thinking. Each property is designed to the highest specifications to reflect our renowned standards in premium condominiums. Nitesh Estates provides spacious residences that are set in the best locations, offering the perfect getaway to home. Here’s an update on the progress of your home at Nitesh Caesars Palace. With Best Wishes, Samiksha Shekhar Assistant Manager - Customer Relations Nitesh Caesars Palace |
|||||||||||||||||
|
|
|
|
|||||||||||||||
|
Block A · Door Shutter Fixing 14th Floor in progress. · Flooring 17th Floor in progress. · Elec. Wiring 13th Floor in progress. |
Block B · External Paint – Primer coat in progress. Door Shutter Fixing 3rd Floor in progress. · Flooring 10th Floor in progress. · Elec. Wiring 3rd Floor in progress. |
Block C · Door Shutter Fixing 14th Floor in progress. · Window Fixing 15th Floor in progress. · Flooring 10th Floor in progress. · Elec. Wiring 3rd Floor in progress |
|||||||||||||||
|
|
|
|
|||||||||||||||
|
Block D · Door Shutter Fixing 5th Floor in progress. · Window Grill Fixing 12th Floor in progress. · Flooring 10th Floor in progress. |
Block E · Slab 16th Floor in progress. · Masonry 14th Floor in progress. |
Block F · Slab 16th Floor in progress. · Block work 13th Floor in progress. · Door Frame Fixing 4th Floor in progress. |
|||||||||||||||
|
|
|
|
|||||||||||||||
|
Block G · Door Frame Fixing 8th Floor in progress. · Fire work 3rd Floor in progress. · Plastering-Internal- 17th Floor in progress. |
Block H · Door Frame Fixing 8th Floor in progress. · Fire work 4th Floor in progress. · Plastering-Internal- 17th Floor in progress.
|
Club House · 1st Floor Slab/Column in progress. Podium · Ground Floor slab completed. |
|||||||||||||||
|
|
|
|
|
||||||||||||||
|
Compound Wall South Side |
Acid Wash in progress · A Block -4 Flats completed. |
Lift Work in progress · A-Block- 4Flats completed. |
|||||||||||||||
|
|
|
|
|||||||||||||||
|
External Development Manhole in progress Front Compound Wall in progress Plantation in Progress Grilling Fixing is completed |
Scaffolding for External Painting
|
||||||||||||||||
|
|
|
|
|||||||||||||||
|
Waterproofing |
Plantation on Progress
|
STP Plant room Internal Plastering · Plastering( External &Internal) Completed |
|||||||||||||||
|
|
|||||||||||||||||
|