Pak Agus,
Menurut info dari NSN (internal schedule), cut over di Balikpapan akan di mulai 5 Oct, tetapi belum fix.
Thanks and Regards,
Rudin F. Simanullang
P Before you print think about the environment.
From: Hadi
Rosmardiansyah [mailto:hadi.rosm...@gmail.com]
Sent: Thursday, September 02, 2010
5:17 PM
To: Rudin F. Simanullang
Subject: Re: Cut Over Schedule
Pak Rudin,
ini project schedule per 30-aug. ini masih internal dan belum 100% fix.
jadi buat pegangan dulu aja dan bener juga schedule tim DT sudah harus di
siapkan.
br,
hadi
2010/9/2 Rudin F. Simanullang <rudin.si...@ptnw.co.id>
Pak Hadi,
Bisa minta tolong di-share cut over schedule bos? Karena kami butuh utk mempersiapkan tim DT.
Thanks and Regards,
Rudin F. Simanullang
P Before you print think about the environment.