| Total 112 projects are covered in this issue.
| Updated between Feb 15-Feb 22, 2012
|
|
|
|
|
|
| Earthing In Cutting, Filling And Blanketing For Bridge At Durgapur: Bid invited.
|
|
The project envisages earthing in cutting, filling and blanketing for
formation, extention of minor bridge rcc pavement floor and ...Read More
|
|
| Foot Over Bridge At Jhansi And Gwalior Stations : Bid invited.
|
|
The project envisages 6. 1 metre wide foot over Bridge at Jhansi and
Gwalior stations of Jhansi division at Jhansi. The estimated ...Read More
|
|
| Indian Railway is planning a aluminium coach factory in Palakad
|
|
Railway Ministry is planning to sett up of a new unit for manufacturing
the state-of-the-art aluminium coaches at Palakkad in Kerala. The ...Read More
|
|
| Construction Of Bridge At Allahabad: Bid invited.
|
|
The project envisages construction Of Bridge At Allahabad. The estimated cost is Rs. 7,22,00,000/-...Read More
|
|
| Strengthening Of Bridge And 406 By RCC Jacketing In Connection At Vaishali: Bid invited.
|
|
Mahboob Alam East Central Railway Vaishali - Bihar - 844 101 India Phone No +91-6224272447 Fax No +91-6224274746 Email ...Read More
|
|
|
|
|
|
| Saudi Arabian Mining Co (Maaden) plans a phosphate project in Waad Al-Shimal City
|
|
Saudi Arabian Mining Co (Maaden) plans to invest 21 billion riyals ($5.6
billion) in a phosphate project in Waad Al-Shimal City for ...Read More
|
|
| Praxair India is expanding industrial gases capacity in Thane
|
|
Praxair India is expanding industrial gases capacity from 294 lakh
hellium per year to 460 lakh hellium per year at Murbad in Thane ...Read More
|
|
| Sesha Sai Chemicals plans to set up a synthetic organic chemicals unit
|
|
Sesha Sai Chemicals plans to set up a synthetic organic chemicals unit
with a capacity of 300 million tpm at Kandivalasa in Vijayanagaram ...Read More
|
|
| Amway India Enterprise plans to set up a cosmetics unit
|
|
Amway India Enterprise plans to set up a cosmetics unit in India.
...Read More
|
|
| Andhra Sugars plans to set up a basic inorganic chemicals unit
|
|
Andhra Sugars plans to set up a basic inorganic chemicals unit with a
capacity of 33,000 tpa at Parawada in Visakhapatnam district ...Read More
|
|
| Rajshree Sugars & Chemicals plans to set up distillery unit in TN
|
|
Rajshree Sugars & Chemicals plans to set up distillery unit with
capacity of 80 klpd at Semmedu in Viluppuram district of Tamil Nadu.
The ...Read More
|
|
| Mula SSK plans to expand an anhydrous alcohol unit
|
|
Mula SSK plans to expand an anhydrous alcohol unit with a capacity from
60,000 liter per day to 90,000 liter per day at Sonai, Newasa ...Read More
|
|
| Mehta Petro Refineries plans to set up chemicals unit
|
|
Mehta Petro Refineries plans to set up chemicals unit with a capacity of
500 tpd at Dahej Industrial Area in Bharuch district of Gujarat....Read More
|
|
| Kiri Industries is expanding sulphur dichloride capacity
|
|
Kiri Industries is expanding sulphur dichloride capacity from 1,50,000
tpa to 2,02,800 tpa at Dudhwada in Vadodara district of Gujarat. The ...Read More
|
|
|
|
|
|
| Aurobindo Pharma is setting up a bulk drugs unit
|
|
Aurobindo Pharma is setting up a bulk drugs unit at Pydibhimavaram
Village in Srikakulam district of Andhra Pradesh. The facility ...Read More
|
|
|
|
|
|
| Six laning of Ahmedabad-Vadodara and Samakhiali sections: IRB achieved financial closure
|
|
NHAI is to take uo two sction in Gujarat under NHDP Phase V. EoI has
also been invited for the projects. The details as follows; Six ...Read More
|
|
| Construction Of Bridges At Harda : Bid invited.
|
|
The project envisages construction Of Bridges At Harda. The estimated cost is Rs. 6,37,37,000/-...Read More
|
|
| Four/six laning of NH 66 between Kundapur - Goa Via Karwar: Bid invited
|
|
NHAI to take up the 187 km stretch on the National Highway 66 between
Kundapur and Goa border via Karwar is all set for widening. The ...Read More
|
|
| Kochi ring road project:
|
|
The propsed 15 Km rign road which will pass through from the Vyttila
Mobility Hub, will touch Kaniyampuzha, Seaport-Airport Road and ...Read More
|
|
| Emmar properties to build a glass tunnel to connect the Dubai Mall to Burj Khalifa Metro Station
|
|
Emmar properties to build a glass tunnel to connect the Dubai Mall to
Burj Khalifa Metro Station the number of mall visitors is expected ...Read More
|
|
| Four lanning of Mukamma to Munger stretch of NH : C&C Construction to execute
|
|
The project envisages four lanning of 70-km Mukamma to Munger stretch with an estimated cost of Rs 444 crore....Read More
|
|
| four laning of Muzaffarpur to Sonbarsa National Highway: C&C to execute
|
|
The project envisages four laning of 84 km stretch connecting Muzaffarpur to Sonbarsa with an estimated cost of 656 crore....Read More
|
|
| four laning of Patna to Bakhtiarpur highway stretch: C&C to execute
|
|
The project envisages four laning of 50-km stretch between Patna to
Bakhtiarpur, The estimated total cost of the project is Rs 908 ...Read More
|
|
| Construction Of Major Bridge Across Indrayani River Charholi Kelgaon Dudulgaon: Bid invited.
|
|
The project envisages construction of major bridge across Indrayani
river Charholi Kelgaon Dudulgaon Alandi diversion road tal. Khed, ...Read More
|
|
| Road construction work between Barabanki-Bahraich-Nanpara-Rupaidiha At Lucknow: Bid invited.
|
|
The project envisages overlay with WBM & SDBC 25 MM in completely
damaged abadi portions in km. 12, 20, 26,50,58,59,63,67,78, periodic ...Read More
|
|
| 4/6 Laning Work Of NH 200 From Raipur To Bilasur In Chhattisgarh State: Bid invited.
|
|
The project envisages 4/6 laning work of NH 200 from Raipur to Bilasur
in Chhattisgarh state. The estimated cost 12,16,03,00,000/-...Read More
|
|
| Widening And Reconstruction Of Hata Swaspur Musabani Road At Ranchi: Bid invited.
|
|
The project envisages Widening and reconstruction of hata swaspur
musabani road at Ranchi. The estimated cost is Rs. 70,99,28,400/-...Read More
|
|
| Strengthening The Road In Km 0/0 -7/0 And 18/0 -19/0 Including Raising Dip At Salem: Bid invited.
|
|
The project envisages strengthening The Road In Km 0/0 -7/0 And 18/0
-19/0 Including Raising Dip At Salem. The estimated cost is Rs. ...Read More
|
|
| Improvements To Riding Quality In Dindugal-Bangalore road: Bid invited.
|
|
The project envisages improvements to riding quality in km. 81/0-86/0,
92/0-104/0 and 119/0-122/0 Dindugal-Bangalore road, (National ...Read More
|
|
| NHAI plans six lane of Ahmedabad-Vadodra section along NH-8: Achieved financila closure
|
|
NHAI plans six-laning of 102-km stretch of NH-8 along the
Ahmedabad-Vadodra section. The estimated project cost is Rs 3,600
crore. IRB ...Read More
|
|
|
|
|
|
| Salalah Medical City project
|
|
Apex Medical Group (AMG), a part of top Saudi conglomerate AlJoaib
Holding, has completed the market feasibility study of its mammoth ...Read More
|
|
|
|
|
|
| Aditya Birla Group to set up Cement unit in Bihar
|
|
Aditya Birla Group to invest Rs 500 crore in Bihar in the next six months to set up a cement unit....Read More
|
|
| Birla Corporation is expanding cement capacity
|
|
Birla Corporation is expanding cement capacity from 0.53 million tpa to
0.68 million tpa in Rae Bareilly district of Uttar Pradesh.
...Read More
|
|
| Blueart Granito to setting up a ceramic tiles unit
|
|
Blueart Granito plans to setting up a ceramic tiles unit with a capacity
of 84,000 metres per annum at Morbi in Rajkot district of ...Read More
|
|
| H R Johnson is setting up a greenfield plant to produce engineered marble
|
|
H R Johnson is setting up a greenfield plant, The project would come up
by February 2012 to produce one million sq.m of engineered ...Read More
|
|
| Chettinad Cement is setting a unit in Gulbarga: Nearing completion
|
|
Chettinad Cement Corporation is setting up a cement facility in Gulbarga
District of Karnataka with an expected investment of Rs. ...Read More
|
|
|
|
|
|
| Construction Of Canal System Including Earth Work, Lining And Canal Structure at MP: Bid invited.
|
|
The project envisages construction of canal system including earth work,
lining and canal structure of runj dam project distt. Panna ...Read More
|
|
| Modernization Of Godavari Delta Irrigation System For Reconstruction Of Kakaraparru Regulator: Bid .
|
|
The project envisages Godavari delta irrigation system for
reconstruction of Kakaraparru regulator & navigation lock @ km. 11.
773 ...Read More
|
|
|
|
|
|
| Designing And Construction Of Water Treatment Plant at Vadodara: Bid invited.
|
|
The project envisages designing and construction of water treatment plant. The estimated cost is Rs. 46.60 crores...Read More
|
|
|
|
|
|
| Shangri-La Hotels and Resorts is constructing a resort in Hambantota.
|
|
Shangri-La Hotels and Resorts is constructing a 300-room city resort in
Hambantota. Shangri-La had purchased a property in Hambantota ...Read More
|
|
| Shangri-La Hotels and Resorts plans a 5 star hotel in Colombo
|
|
Shangri-La Hotels and Resorts, is to start the construction work of the Colombo luxury hotel project. Shangri-La had purchased ...Read More
|
|
|
|
|
|
| Fleetguard Filters is implementing a filtering and purifying machinery unit
|
|
Fleetguard Filters is implementing a filtering and purifying machinery
unit with a capacity of 55 lakh numbers per year at Bellur ...Read More
|
|
| Afflatus Gravures plans to set up a printing machineries unit
|
|
Afflatus Gravures plans to set up a printing machineries unit at
Umbergaon in Valsad district of Gujarat. February 2012: The company ...Read More
|
|
| Diamond Power to expand conductor and rode manufacturing capacity
|
|
Diamond Power Infrastructure Ltd (DPIL), has drawn up an expansion plan
at an investment of about Rs 750 crore. The board of directors ...Read More
|
|
| Graphite India plans expansion: Nearing completion
|
|
Graphite electrodes manufacturer Graphite India Ltd (GIL) will expand
the capacity of its Durgapur plant in West Bengal to 20,000 ...Read More
|
|
| Titan Industries is setting up a photographic equipments unit
|
|
Titan Industries is setting up a photographic equipments unit with a
capacity of 8 lakh numbers per year at Pantnagar in Udham Singh ...Read More
|
|
| KEI Industries plans to set up a insulated wires and cables unit
|
|
KEI Industries plans to set up a insulated wires and cables unit at Rakholi village in Dadra & Nagar Haveli....Read More
|
|
| Aishwarya Telecom is planning a missile communication equipment mfg plant in AP
|
|
Aishwarya Telecom is planning a missile communication equipment
manufacturing plant in dist. Hyderabad, AP. Further details are yet ...Read More
|
|
| Imperial Enterprises plans to set up an airconditioners and refrigerators mfg unit
|
|
Imperial Enterprises plans to set up an airconditioners and
refrigerators manufacturing unit at Shop No.485/G-3, J Block, Landscape ...Read More
|
|
| Surana Ventures plans to set up a solar photovoltaic cells unit
|
|
Surana Ventures plans to set up a solar photovoltaic cells unit at
Cherlapally in Ranga Reddy district of Andhra Pradesh. October ...Read More
|
|
|
|
|
|
| Raja Udyog is setting up a biscuits unit in Uttarakhand
|
|
Raja Udyog is setting up a biscuits unit with a capacity of 100 tpm at Sector 1B in Hardwar district of Uttarakhand.
...Read More
|
|
|
|
|
|
| Metro Cash & Carry is planning to double its stores
|
|
Metro Cash & Carry is planning to double its stores in the country
by next year and will continue with its aggressive expansion mode ...Read More
|
|
|
|
|
|
| Hindusthan National Glass & Industries is setting up a glass bottles unit
|
|
Hindusthan National Glass & Industries is setting up a glass bottles
unit with a capacity of 200 tpd at Behror, Neemrana in Alwar ...Read More
|
|
| Hindusthan National Glass plans manufacturing facility in the Neemrana
|
|
Hindusthan National Glass Industries Ltd (HNGIL) plans to invest about
Rs 2,500 crore over 7-8 years on a new manufacturing facility ...Read More
|
|
| Megha Fibre Glass Industries is expanding glass fibre
|
|
Megha Fibre Glass Industries is expanding glass fibre capacity from 150
million tpa to 300 million tpa at Plot No. 36, 39, 37(P), ...Read More
|
|
|
|
|
|
| Sneha Farms is setting up a rice bran oil unit in AP
|
|
Sneha Farms is setting up a rice bran oil unit with a capacity of 300
tpd at Chenjerla Village in Karimnagar district of Andhra Pradesh.
...Read More
|
|
| Kirti Agrotech is setting up a solvent extraction unit
|
|
Kirti Agrotech is setting up a solvent extraction unit with a capacity
of 500 tpd at Hingoli in Pune district of Maharashtra. The ...Read More
|
|
| Sri Venkatarama Oil Industries plans to expand rice bran oil capacity
|
|
Sri Venkatarama Oil Industries plans to expand rice bran oil capacity
from 14,553 tpa to 24,948 tpa at Hussainpuram, Samalkot in East ...Read More
|
|
| Frigerio Conserva Allana plans to set up a vegetable oils unit
|
|
Frigerio Conserva Allana plans to set up a vegetable oils unit with a
capacity of 1.53 lakh tpa at Mutthukur in Nellore district of ...Read More
|
|
|
|
|
|
| Inabensa Bharat plans to set up a steel structures unit
|
|
Inabensa Bharat plans to set up a steel structures unit with a capacity
of 25,000 tpa at Halol in Panchmahals district of Gujarat. The ...Read More
|
|
| Citizen Metalloys plans to set up a copper wire rods unit in Gujarat
|
|
Citizen Metalloys plans to set up a copper wire rods unit with a
capacity of 5,000 tpa in Ahmedabad district of Gujarat. The project ...Read More
|
|
| Sohar steel project: Foundation stone laid
|
|
Takamul Investment Company SAOC, is implementing a specialty steel
products plant at Sohar at a cost of approximately USD 30 million. The ...Read More
|
|
| K Energy Company is setting up an integrated steel unit
|
|
K Energy Company is setting up an integrated steel unit at Urga village
in Korba district of Chhattisgarh. The project to spread ...Read More
|
|
| R S Infra Transmission plans to set up a structural steel unit
|
|
R S Infra Transmission plans to set up a structural steel unit with a
capacity of 1 lakh tpa at Metal Park in Raipur district of Chhattisgarh.
February ...Read More
|
|
| Jeevaka Industries is planning a 200 to 400 TPD billets mfg expansion
|
|
Jeevaka Industries is planning a 200 to 400 TPD billets manufacturing
expansion at Nasthipur, dist. Medak, AP. Equipment suppliers ...Read More
|
|
|
|
|
|
| SEL Textiles plans to set up a cotton yarn unit in Punjab
|
|
SEL Textiles plans to set up a cotton yarn unit with a capacity of 1.38
lakh spindles per year at Lambi in Muktsar district of Punjab.
...Read More
|
|
| Salguti Industries is expanding cotton and blended fabrics capacity in AP
|
|
Salguti Industries is expanding cotton and blended fabrics capacity from
15,000 metres per month to 40,000 metres per month at Gollapalli ...Read More
|
|
| MG Cotton Co. plans to set up knitted cotton garments unit
|
|
MG Cotton Co. plans to set up knitted cotton garments unit with a
capacity of 15 lakh pieces per year at Avinashi in Coimbatore district ...Read More
|
|
| Ganga Spintex is setting up a cotton yarn unit
|
|
Ganga Spintex is setting up a cotton yarn unit with capacity of 13,000
spindles in Mansa district of Punjab. The project will spared ...Read More
|
|
|
|
|
|
| Ajmera Group is developing "Times Square" in Andheri East : Xander Finance to invest
|
|
Ajmera Group. is developing "Times Square"a office & retail project
in Andheri East. Times Square is located on the Andheri-Kurla ...Read More
|
|
| Dubai Mall of Emmar Properties plans to expand by nearly one million sq ft.
|
|
The Dubai Mall of Emmar Properties will now expand by nearly one million
sq ft. The mall is growing and trying to increase its revenues ...Read More
|
|
|
|
|
|
| Mohatadevi Sugar Mills & Agro is setting up a white crystal sugar unit
|
|
Mohatadevi Sugar Mills & Agro is setting up a white crystal sugar
unit with a capacity of 2,500 tccpd at Matori Village in Bid district ...Read More
|
|
| Inbisco India is setting up a sugar confectionery unit
|
|
Inbisco India is setting up a sugar confectionery unit with a capacity
of 4,500 tpa at Medchel in Ranga Reddy district of Andhra Pradesh. The ...Read More
|
|
| Vasantrao Dada Patil SSK is setting up sugar unit and also distillery unit
|
|
Vasantrao Dada Patil SSK is setting up sugar unit with capacity of 2,500
tccpd at Vithewadi, Kalwan taluka in Nashik district of Maharashtra.
The ...Read More
|
|
|
|
|
|
| Myntdu Leshka HE Scheme : Ready to commission
|
|
The State Electricity Board of Meghalaya is setting up an 84-MW Myntdu
Leshka HE project in the Jaintia Hills District of Meghalaya ...Read More
|
|
| OPGC plans second phase expansion in Orissa: set to place order for BTG package by August
|
|
The company is focusing on the second phase expansion of OPGC located at
Ib valley in Jharsuguda district. The expansion comprises ...Read More
|
|
| Vishwanath Sugar plans to double capacity of its cogen plant
|
|
Vishwanath Sugar and Steel Industries Limited plans to enhance the
capacity of its co-generation unit to 66.40 Mw by installing new ...Read More
|
|
| NTPC's thermal power project at Kudgi :
|
|
National Thermal Power Corporation (NTPC) will develop a 4,000-MW
greenfield thermal power project worth Rs. 20,000 crore at Kudgi ...Read More
|
|
| Demwe Lower Hydroelectric project : received MoEF approval
|
|
Government of Arunachal Pradesh (GoAP) awarded the Demwe Hydro Electric
Project with an installed capacity of 3000 MW, under Public ...Read More
|
|
| OPG Power Gujarat plans to set up a group captive power unit : National Green Tribunal
|
|
OPG Power Gujarat plans to set up a group captive power unit of 300 MW
{2x150 MW ( or 15%)} in Kachchh district of Gujarat on EPC/BTG/BOP ...Read More
|
|
| Ambuja Intermediates plans to set up a 1.5 MW wind based power unit
|
|
Ambuja Intermediates plans to set up a 1.5 MW wind based power unit at
Suthri in Kachchh district of Gujarat. Work on the project ...Read More
|
|
| Bin Qasim Power Plant (BQPP) coal conversion project:
|
|
The coal conversion project aiming to convert its 1,260MW (210MW X 6
units) Bin Qasim Power Plant (BQPP) into a coal-fired generation ...Read More
|
|
| A A Energy plans to expand biomass based power capacity
|
|
A A Energy plans to expand biomass based power capacity from 10 MW to
17.5 MW at Desaiganj in Gadchiroli district of Maharashtra. ...Read More
|
|
| Tata Power plans to set up solar power project in Gujarat: Commissioned
|
|
Tata Power plans to set up 50 Mw solar photovoltaic power project at
Mithapur in Gujarat. The proposed project at Mithapur will ...Read More
|
|
| Shri Lakshmi Groups is setting up a 300MW coal based power unit at Bitkuli: Bid invited for BTG pkg
|
|
The project envisages setting up a 300 +/- 20% MW independent coal based
power unit at Bitkuli/ Pasid village, Bhatapara tehsil in ...Read More
|
|
| Regulus Power is planning a 400 MW coal based power project in Vemulapalli
|
|
Regulus Power plans to set up a 400 MW coal based power unit at
Vemulapalli village, Mandapeta in East Godavari district of Andhra ...Read More
|
|
| Electrosteel Castings plans to set up a 1,200 MW coal based power unit
|
|
Electrosteel Castings plans to set up a 1,200 MW coal based power unit
in Purulia district of West Bengal. April 2009: The company ...Read More
|
|
| Tata Power and Industrial Energy is setting up of 450 MW Coal based power unit at Kalinganagar
|
|
Tata Power and Industrial Energy is setting up of 450 MW (3x150 MW)
coal-cum-gas based power unit at Kalinganagar in Jajpur district ...Read More
|
|
| Tata Power and Industrial Energy is setting up of 202.5 MW gas based power unit at Kalinganagar
|
|
Tata Power and Industrial Energy is setting up of 202.5 MW (3x67.5 MW)
gas based power unit at Kalinganagar in Jajpur district of ...Read More
|
|
| Patni Energy plans to set up a coal based power unit
|
|
Patni Energy plans to set up a coal based power unit at Alibag in
Raigarh district of Maharashtra. The unit would be implemented ...Read More
|
|
| Lanco Infratech to implementing a (500 MW) Hydel Power Plant
|
|
Lanco Infratech is implementing a (500 MW) Hydel Power Plant in Sikkim. The main river is Teesta river. Alstom Projects India ...Read More
|
|
| Dhariwal Infrastructure is setting up 60 MW coal based captive power unit
|
|
Dhariwal Infrastructure is setting up 60 MW coal based captive power
unit at Mul in Chandrapur district of Maharashtra. September ...Read More
|
|
| Jeevaka Industries plans to set up a 12 MW coal based power unit
|
|
Jeevaka Industries plans to set up a 12 MW coal based power unit at
Nasthipur Hatnoora in Medak district of Andhra Pradesh. The ...Read More
|
|
| Tata Power Company plans to set up a Dugar hydel power unit in HP
|
|
The project envisages setting up a 236 MW Dugar hydel power unit at
Chenab Valley in Kinnaur district of Himachal Pradesh. Tata ...Read More
|
|
| GEMAC Energy plans to set up a 1,320 MW coal based power unit in TN
|
|
GEMAC Energy, a group company of GEMAC Group plans to set up a 1,320 MW
(2 x 660 MW) coal based power unit in Cuddaore district of ...Read More
|
|
| Annapurna Renewables plans to set up a poultry litter based power unit in AP
|
|
Annapurna Renewables plans to set up a 7.5 MW poultry litter based power
unit at Tukkuluru Village, Muzvid in Krishna district of ...Read More
|
|
| Lanco Green Power is setting up the 70-MW Budhil Hydel Power Project
|
|
Lanco Green Power, part of the Hyderabad based Lanco Group, is setting
up the 70-MW Budhil Hydel Power Project in Himachal Pradesh. ...Read More
|
|
| 2,640 MW Amravati Thermal Power Project: Areva T&D to supply power transformers
|
|
Indiabulls Power Services, a subsidiary of Indiabulls Real Estate, is
setting up 2,640 MW Amravati Thermal Power Project at Nandgaonpeth ...Read More
|
|
| JSW Energy to set up power project in Chhattisgarh:Funds to be raised for the project
|
|
The JSW group-promoted JSW Energy has signed a memorandum of
understanding (MoU) with the Chhattisgarh Government for setting up
1,320 ...Read More
|
|
| Athena Chhattisgarh plans to set up a 1200 MW Coal based power project
|
|
Athena Chhattisgarh Power is planning a 1200 MW (2x600 Mw) Coal based
power project in Singhitarai, district Janjgir-Champa, Chhattisgarh. ...Read More
|
|
| GMR plans to implement 3x100 MW Alaknanda hydro power project
|
|
GMR (Badrinath) Hydro Power Generation plans to implement 3x100 MW
Alaknanda hydro power project (AHEP), located over river Alaknanda ...Read More
|
|
| Himachal Pradesh State Electricity plans to set up 240 MW hydel power unit
|
|
Himachal Pradesh State Electricity Board plans to set up 240 MW (3x80
MW) power unit at Kutehr in Chamba district of Himachal Pradesh. ...Read More
|
|
| Lanco Infratech's Phatabyung hydro electric project in Uttarakhand
|
|
Lanco Infratech Ltd plans to set up a new hydro power plant. The 76-MW
Phatabyung hydro electric project will be set up in Uttarakhand ...Read More
|
|
| K Energy is planning a 90 MW coal based power project
|
|
K Energy Company is planning a 90 MW coal based power project at Urga,
dist. Korba, Chhattisgarh. Equipment suppliers are yet to be ...Read More
|
|
| Rosa Power Project Phase I & II: Fully operational by next month
|
|
RPSCLis developing a 600 MW coal-fired power project at Rosa village in
Shahjahanpur, Uttar Pradesh, Rosa Phase I. Rosa Phase I ...Read More
|
|
|
|
|
|
| Kochi refinery is setting up sulphur recovery unit : scouting for JV Partner
|
|
Kochi Refinery is presently scouting for a joint venture partner for a
new sulphur recovery unit which is part of its Phase I expansion ...Read More
|
|
| Ambalamugal to FACT sulphur pieplien project:
|
|
Bharat Petroleum Corporation Ltd (BPCL), is planning to build a
pipeline to transport molten sulphur from its refinery in Ambalamugal ...Read More
|
|
|
|
|
|
| Deoghar international airport expansion project: MoU signed
|
|
The airport will be developed on 675 acres which has been acquired by
the state government. The total cost of the project has been ...Read More
|
|
|
|
|
|
| Nirmal Lifestyle launches "Zircon & Amethyst " at Mulund
|
|
Nirmal Lifestyle launches new residential development Zircon &
Amethyst located at Mulund West in Mumbai. The project offers luxurious ...Read More
|
|
| Kamrup Housing Projects to develop a apartmement complex in Greater Noida
|
|
Kamrup Housing Projects to develop a apartmement complex in Greater Noida over the next 3-4 years....Read More
|
|
| Kamrup Housing Projects is developing
|
|
Kamrup Housing Projects is developing a housing project in Guwahati. The
company has already acquired the land and received all necessary ...Read More
|
|
| Construction of parliament building at Kabul : C&C to execute
|
|
CPWD, India is constructing the Afghanistan's parliament building,
entailing an investment of $95 million, by June, 2013. The project ...Read More
|
|
|
|