Parsing start and Finish dates

18 views
Skip to first unread message

PeteA

unread,
May 17, 2013, 10:55:43 AM5/17/13
to mylifeo...@googlegroups.com
Am I missing a trick? I can parse the finish date of a task, and I can parse the start date (using -s), but I can't parse both together. Is there a way, or is it not (yet) possible?
Many thanks for any input,
Pete

Lisa Stroyan

unread,
May 17, 2013, 11:30:46 AM5/17/13
to Group, MyLifeOrganized
it's a long-standing problem. :-) Annoys the heck out of me. The solution is to use -L, lead time. 


--
You received this message because you are subscribed to the Google Groups "MyLifeOrganized" group.
To unsubscribe from this group and stop receiving emails from it, send an email to mylifeorganiz...@googlegroups.com.
To post to this group, send email to mylifeo...@googlegroups.com.
Visit this group at http://groups.google.com/group/mylifeorganized?hl=en.
For more options, visit https://groups.google.com/groups/opt_out.
 
 



--
Lisa


Lisa Stroyan, mailto: lstr...@gmail.com

PeteA

unread,
May 17, 2013, 11:44:59 AM5/17/13
to mylifeo...@googlegroups.com
Ah yes, I've just tried that - and it works, but it takes a bit more calculation, doesn't it.
Andrey, please can we make it simpler? (Just like that!)