Hi Alyona,
Thanks for your reply and the link. You say that but, having read through the link, I'm struggling to find how to do that (I have ver 5.2.1).
What I did was
Step 1 - add all of my task types to the All Tasks section of the Outline, and add all of my Project Types to the Projects section of the Outline. Then I selected My Health Workspace, opened Manage Views and deselected all of the tasks and projects that shouldn't be visible in my Health Workspace, as you can see in the attached image (Views for Health WorkSpace.png).
Step 2 - Right clicked on the Workspace Tab to set this as a default (as you can see in Setup for Health Workspace.png).
Step 3 - Switched to my Efficiency & Control Workspace, opened Manage Views, then deselected all of the Health Tasks and Projects that shouldn't be visible in my Efficiency & Control Workspace, and then Selected the Tasks and Projects that should be visible (as you can see in Views for Efficiency.png)
Step 4 - Switched back to my Health Workspace but there and selected restore defaults, but the views remained the same, i.e. they didn't change from the setup of My Efficiency Workspace, Then when I tried to repeat all of this the options to set or restore the default were greyed out (I tried locking and unlocking the defaults)
Step 5 - Manually reset the views of the Tasks so that they matched what they should have been for my Health Workspace, but when I then clicked on my Efficiency WorkSpace Tab and then right clicked the Restore option was also greyed out).
If it's not clear from my process description above, I just want to be able to vies 4 specific Task and project types in my Health WorkSpace, and a different set of 2 Specific task and project types in my Efficiency and Control Workspace. How do I do that?
Regards,
Gerry