We started Sprint 2 of Q2 today. While there are a few areas of fine-tuning
of user stories, we¹re basically ready to go. Here¹s an overview of the
work we¹re we¹re doing this sprint:
Dates
April 24 May 9
Goals/Themes
Some of the topics we¹re covering this sprint include documenting different
types of <input> element pages, utilizing the new combat data schema, Fx 55
documentation updates, live sample code editor for A/B testing of
prototypes, removing KumaScript editing code from Kuma, and developing the
plan to migrate community communication over to Discourse.
Full list of topics in the sprint document:
https://docs.google.com/a/mozilla.com/document/d/1Ur_9YRPLN4-IQXXX7TIWsEJrhi
8UouXbedFaRid8wcM/edit?usp=sharing
User Stories
Taiga board:
https://tree.taiga.io/project/viya-mdn-durable-team/taskboard/2017-q2-sprint
-2
Duration
12 days as usual
Stand-up Schedule
* 8:30AM PDT Mon Thurs.
*
* Mondays/Wednesdays: Development work
*
* Tuesdays/Thursdays: Content/Contributor Engagement work
Team Availability
* Generally OK (some PTO¹s, public holiday for some on 1st May)
Special meetings, offsites, etc.
None scheduled so far
Please let me know if there are any questions.
--Vik