Hi guys,

happy new year to everyone!

I know that I've been awfully quiet on the state of things in the
Thunderbird world. I'm sorry for that. I was trying to nail down some
stuff (release scheduling, website l10n story of which I will talk more
in a later post), which took longer than anticipated.

I want to inform you about our release schedule for the upcoming
Thunderbird releases.

* First of all the dates for the upcoming Thunderbird beta2 release:

- Slushy string freeze: January 29th (Thursday)
- Slushy code freeze: February 3rd (Tuesday)
- Firm code/string freeze: February 5th (Thursday)
- l10n-mozilla-1.9.1 freeze: February 8th (Sunday)
- Gozer starts the builds: February 9th (Monday)

We've tried to emulate what the Firefox devs did for their beta2
release, as we got the impression that this worked pretty well.

The idea is to have all string-related work done by the slushy
string freeze date and all other code-related work plus the
late-string work by the slushy code freeze date. Late string
changes will require an additional approval by our TB3 beta2
release driver Bryan Clark (clarkbw on IRC).

The firm freeze date would be for fixing remaining bugs and
regressions found in the nightlies and the l10n-mozilla-1.9.1 date
would be the last time by which we would accept changes in
localizations.

* We know that this is a tough schedule and that this announcement
comes pretty late. Therefore if significant objections are raised
by you, we will reconsider this schedule and will discuss, whether
this warrants a pushback of this schedule by one week.

* Thunderbird drivers have also evaluated the current state of things
and have decided to add another beta release (beta3) to the release
schedule. A firm decision on a release date has not yet been made,
but it is probably safe to say, that beta3 will be released
somewhere between the end of March and the end of April.

If you have any questions or concerns, please do not hesitate to
respond here in this thread.

Cya
Simon
--
Thunderbird/Calendar Localisation (L10n) Coordinator
Thunderbird l10n blog: http://thunderbird-l10n.blogspot.com
Calendar website maintainer: http://www.mozilla.org/projects/calendar
Calendar developer blog: http://weblogs.mozillazine.org/calendar

Eric Valette

unread,
Jan 20, 2009, 5:11:07 AM1/20/09
to Simon Paquet
Simon Paquet wrote:
> Hi guys,
>
> happy new year to everyone!
>
> I know that I've been awfully quiet on the state of things in the
> Thunderbird world. I'm sorry for that. I was trying to nail down some
> stuff (release scheduling, website l10n story of which I will talk more
> in a later post), which took longer than anticipated.

Any info if lightning integration is planned or not for beta2 and if not
for beta2 when? beta3, 1.0?

I recall thunderbird 2 user are left with a unpolished, dead end 0.9
that hardly interoperates with ooulook.

-- eric

Ricardo Palomares Martí­nez

unread,
Jan 22, 2009, 12:24:38 PM1/22/09
to
Simon Paquet escribió:

> I want to inform you about our release schedule for the upcoming
> Thunderbird releases.
>
> * First of all the dates for the upcoming Thunderbird beta2 release:
>
> - Slushy string freeze: January 29th (Thursday)
> - Slushy code freeze: February 3rd (Tuesday)
> - Firm code/string freeze: February 5th (Thursday)
> - l10n-mozilla-1.9.1 freeze: February 8th (Sunday)
> - Gozer starts the builds: February 9th (Monday)
> (...)

> The firm freeze date would be for fixing remaining bugs and
> regressions found in the nightlies and the l10n-mozilla-1.9.1 date
> would be the last time by which we would accept changes in
> localizations.


Since February 5th in PDT timezone means, in practice, February 6th
for european people, the dates fall just in the FOSDEM weekend. Either
advancing dates so thursday 5th is the l10n lock-down, or extending it
a bit longer to Feb 9th evening would be better. Even though we have
WiFi at FOSDEM, there could be some problems connecting (I for one
won't have network access at the hotel, and my laptop is a bit picky
regarding WiFi connectivity).

Ricardo

Simon Paquet

unread,
Jan 22, 2009, 4:53:08 PM1/22/09
to
Eric Valette wrote:

>> happy new year to everyone!
>>
>> I know that I've been awfully quiet on the state of things in the
>> Thunderbird world. I'm sorry for that. I was trying to nail down some
>> stuff (release scheduling, website l10n story of which I will talk more
>> in a later post), which took longer than anticipated.
>
>Any info if lightning integration is planned or not for beta2 and if not
>for beta2 when? beta3, 1.0?

I can't tell you anything definitive right now. Hopefully I can give you
something more concrete in a few days.

Cya
Simon Paquet

Simon Paquet

unread,
Jan 22, 2009, 4:52:16 PM1/22/09
to
Ricardo Palomares Martí­nez wrote:

>Since February 5th in PDT timezone means, in practice, February 6th
>for european people, the dates fall just in the FOSDEM weekend. Either
>advancing dates so thursday 5th is the l10n lock-down, or extending it
>a bit longer to Feb 9th evening would be better. Even though we have
>WiFi at FOSDEM, there could be some problems connecting (I for one
>won't have network access at the hotel, and my laptop is a bit picky
>regarding WiFi connectivity).

Thanks for your feedback, Ricardo. I totally missed that. Partly based on
your feedback, we've decided to postpone the release. See my other post
for details.