Future of Connected Devices Data Sync

9 views
Skip to first unread message

Michiel de Jong

unread,
Dec 18, 2015, 9:11:01 AM12/18/15
to dev-fxos-sync
Hi all,

Assuming we're not giving up on our mission (see other thread), and given that all projects within Connected Devices now need to go through the gating process, we have a few options, for instance:

1) Disband the Data Sync project as such, and restrict scope to trains that have already been proposed, i.e. splitting activities into 'data sync for smart TV', 'data sync for home automation', etc.
2) Create a pitch deck about Data Sync
3) Propose 'cross-browser gaia' as one of the projects to continue within connected devices (or hope at least some gaia apps will continue to be actively developed and continue to have a significant user base), and keep working on adding data sync to gaia apps (not just Smart TV)

Proposals for the gating process need:
* a product manager (Preeti?)
* a pitch deck using Lean Canvas

What are people's thoughts about this? Shall we have a meeting to discuss?


Cheers,
Michiel

Michiel de Jong

unread,
Dec 21, 2015, 3:39:03 AM12/21/15
to dev-fxos-sync
On Fri, Dec 18, 2015 at 3:10 PM, Michiel de Jong <mbde...@mozilla.com> wrote:
Hi all,

Assuming we're not giving up on our mission (see other thread), and given that all projects within Connected Devices now need to go through the gating process, we have a few options, for instance:

1) Disband the Data Sync project as such, and restrict scope to trains that have already been proposed, i.e. splitting activities into 'data sync for smart TV', 'data sync for home automation', etc.
2) Create a pitch deck about Data Sync
3) Propose 'cross-browser gaia' as one of the projects to continue within connected devices (or hope at least some gaia apps will continue to be actively developed and continue to have a significant user base), and keep working on adding data sync to gaia apps (not just Smart TV)

I drafted a Lean Canvas for this: https://canvanizer.com/canvas/2OxuBRFcWas
 

Proposals for the gating process need:
* a product manager (Preeti?)
* a pitch deck using Lean Canvas

What are people's thoughts about this? Shall we have a meeting to discuss?

We can discuss in today's team meeting (starting in 20 minutes).
 


Cheers,
Michiel

fjor...@mozilla.com

unread,
Dec 21, 2015, 11:30:46 AM12/21/15
to mozilla-de...@lists.mozilla.org
Hi all,

(and sorry for the last minute post :))


On Friday, December 18, 2015 at 2:11:01 PM UTC, Michiel de Jong wrote:
> Hi all,
>
> Assuming we're not giving up on our mission (see other thread), and given that all projects within Connected Devices now need to go through the gating process, we have a few options, for instance:
>
> 1) Disband the Data Sync project as such, and restrict scope to trains that have already been proposed, i.e. splitting activities into 'data sync for smart TV', 'data sync for home automation', etc.

I would agree with this sentence once we get a bare minimum, I have the feeling our MVP, is very very M, IMO, we should provide at least write support, to being able to say that we have data sync and not just import.

This to me is totally aligned with the new train models, and explorations, since sync capabilities will be needed, write will needed too.

> 2) Create a pitch deck about Data Sync

+1

> 3) Propose 'cross-browser gaia' as one of the projects to continue within connected devices (or hope at least some gaia apps will continue to be actively developed and continue to have a significant user base), and keep working on adding data sync to gaia apps (not just Smart TV)


I think this is outside of the data sync scope. Seems to me that the WADI team is the perfect target for this ;). I'm sure they will like to hear from that topic.

>
>
> Proposals for the gating process need:
>
> * a product manager (Preeti?)
>
> * a pitch deck using Lean Canvas
>
>
> What are people's thoughts about this? Shall we have a meeting to discuss?
>
>
>
>
> Cheers,
>
> Michiel

Cheers,
F.

Michiel de Jong

unread,
Dec 21, 2015, 1:49:42 PM12/21/15
to Francisco Jordano, mozilla-de...@lists.mozilla.org
OK, makes sense! Thanks.

On Mon, Dec 21, 2015 at 5:26 PM, <fjor...@mozilla.com> wrote:
Hi all,

(and sorry for the last minute post :))


On Friday, December 18, 2015 at 2:11:01 PM UTC, Michiel de Jong wrote:
> Hi all,
>
> Assuming we're not giving up on our mission (see other thread), and given that all projects within Connected Devices now need to go through the gating process, we have a few options, for instance:
>
> 1) Disband the Data Sync project as such, and restrict scope to trains that have already been proposed, i.e. splitting activities into 'data sync for smart TV', 'data sync for home automation', etc.

I would agree with this sentence once we get a bare minimum, I have the feeling our MVP, is very very M, IMO, we should provide at least write support, to being able to say that we have data sync and not just import.

This to me is totally aligned with the new train models, and explorations, since sync capabilities will be needed, write will needed too.

> 2) Create a pitch deck about Data Sync

+1


> 3) Propose 'cross-browser gaia' as one of the projects to continue within connected devices (or hope at least some gaia apps will continue to be actively developed and continue to have a significant user base), and keep working on adding data sync to gaia apps (not just Smart TV)


I think this is outside of the data sync scope. Seems to me that the WADI team is the perfect target for this ;). I'm sure they will like to hear from that topic.

>
>
> Proposals for the gating process need:
>
> * a product manager (Preeti?)
>
> * a pitch deck using Lean Canvas
>
>
> What are people's thoughts about this? Shall we have a meeting to discuss?
>
>
>
>
> Cheers,
>
> Michiel

Cheers,
F.
_______________________________________________
dev-fxos-sync mailing list
dev-fx...@lists.mozilla.org
https://lists.mozilla.org/listinfo/dev-fxos-sync

Preeti Sanketh

unread,
Dec 21, 2015, 2:00:56 PM12/21/15
to Michiel de Jong, dev-fxos-sync
Hi All,

Apologize for the delay, but I'm pretty much OOO for the holidays. Please see comments inline.

cheers,
preeti

On Fri, Dec 18, 2015 at 6:10 AM, Michiel de Jong <mbde...@mozilla.com> wrote:
Hi all,

Assuming we're not giving up on our mission (see other thread), and given that all projects within Connected Devices now need to go through the gating process, we have a few options, for instance:

1) Disband the Data Sync project as such, and restrict scope to trains that have already been proposed, i.e. splitting activities into 'data sync for smart TV', 'data sync for home automation', etc.
[Preeti] - Agreed. There are some smaller use cases needed for TV, but perhaps Sean can lead that.
2) Create a pitch deck about Data Sync
[Preeti] - I'd like to wait on this until I get a better sense of our scope for connected devices. I see a need for data exchange, but don't yet know the mechanism proposed; through foxbox and/or cloud etc. 
3) Propose 'cross-browser gaia' as one of the projects to continue within connected devices (or hope at least some gaia apps will continue to be actively developed and continue to have a significant user base), and keep working on adding data sync to gaia apps (not just Smart TV)
[Preeti] I see this being picked up by the WADI team. Again, I'd like to wait until I get more clarity on the underlying trains/strategies.

Proposals for the gating process need:
* a product manager (Preeti?)
* a pitch deck using Lean Canvas

What are people's thoughts about this? Shall we have a meeting to discuss?


Cheers,
Michiel