Theme 6A(Civil Group): You are the in-charge for the design of a flood
control levee for flood control. The project cost is Ksh. 200 million.
The return on investment applicable is 2.5% p.a. What cost of project
flood risk would you allow every year and over the project life of 3
years. List possible components of such risks.
Theme 6B(Electrical Group): You are the in-charge for the design of a
transimssion tower for satellite programme in Kenya. The project cost
is Ksh. 200 million. The return on investment applicable is 7.5% p.a.
What cost of project disaster risk would you allow every year and over
the project life of 5 years. List possible components of such risks.
Theme 6C(Mechanical Group): You are the in-charge for the design of a
new and innovative air cooling system in specially designed rooms at
Konza City in Kenya. The project cost is Ksh. 500 million. The return
on investment applicable is 7.5% p.a. What cost of overall project
risk would you allow every year and over the project life of 10 years.
List possible components of such risks.