I plan on running conduit at the beginning of next week. I'll need some help moving the two benches away from the wall, removing ceiling tiles and other fun stuff. Brett has graciously donated the wire and conduit that will needed to run the sub panel. The overall goal is to install a 60 amp sub panel, 4-6 110v outlets, and two 30A 220v twist lock outlets for the welder and the compressor. This will more than likely take all week to complete.

Dru: If you are able to get a load center, I will need it by Monday. If not Lowe's has an Eaton 125-amp 6 breaker for 22 bucks and the ground bar is another 6 bucks.



--
Ben S. Eishen

773.234.7436 | b...@eishen.com
9160 Hwy. 64, Suite 12-302, Lakeland, TN 38002


Dan Hess

unread,
Oct 3, 2012, 7:14:18 PM10/3/12
to midsout...@googlegroups.com
I'll be there and can help move stuff, but we'll need at least 4 people to move those benches.  I'll also be planning to put an outlet in for the fridge and garage door while you're working in other areas.  

Thanks,

Daniel H.
Google Voice:  (901) 214-5326

- Copying one is plagiarism, copying many is research.

Ben Eishen

unread,
Oct 8, 2012, 3:59:21 PM10/8/12
to midsout...@googlegroups.com
I will be out there at 6:30 to start work today. If anyone would like to help.

--
Ben S. Eishen

773.234.7436 | b...@eishen.com
9160 Hwy. 64, Suite 12-302, Lakeland, TN 38002




Ben Eishen

unread,
Oct 9, 2012, 11:28:40 AM10/9/12
to midsout...@googlegroups.com
We'll be out there at 6:30 again today if you would like to give us a hand. We've managed to get the main power cable pulled and the sub panel hung last night. Today help is needed to move the electronics bench back against the wall and moving stuff away from the back wall of the shop to install receptacles. 

If you are interested in what kind of service in the space, it 3 phase power with a "bastard" leg. It is capable of supplying 120v/208v/240v. To get the single phase 208v service it requires a special delta breaker that were banned in 1978, but 3 phase 240v delta breakers should be available. Our new sub panel will only be supplying single phase 120v/240v.



--
Ben S. Eishen

773.234.7436 | b...@eishen.com
9160 Hwy. 64, Suite 12-302, Lakeland, TN 38002




erik

unread,
Oct 9, 2012, 11:34:00 AM10/9/12
to midsout...@googlegroups.com
Yep... I definitely know some of those words!