How do I enter holidays or days off in a Visio Gantt Chart?

776 views
Skip to first unread message

B@discussions.microsoft.com Laura B

unread,
Nov 4, 2009, 6:02:06 PM11/4/09
to
I need to account for vacations, holidays and other days off when scheduling
my tasks in my Gantt Chart. Any ideas on how to do it?

Laura B

unread,
Nov 5, 2009, 11:34:04 AM11/5/09
to
Thank you for your help ... I was hoping that I wouldn't have to use the more
complicated product - Project. It would be nice if you could set individual
days as "no work" days on a gantt chart in Visio, and have the time period
automatically "skip" that day in the total duration.

"WapperDude" wrote:

> The Visio Gantt Chart is not a full, richly featured product. The features
> you desire are not part of the product. You would need to migrate to MS
> Project or some other dedicated project management software.
>
> Wapperdude