Hello,
in some projects, not all and sometimes not all tasks, the tasks assigned to
resources appears in "My Tasks" menu and are imported to my outlook and they
do not appears in resource "My Task" menu or are imported to theirs outlook.
The resources are defined in resources pool, and they have me defined as PM
and assignment owner.
Thsi don't occurs in every projects and for the same resources in a project
for some task behavs like this and for other don't appears either in PM or
REsource "my task" menu and outlook.

Best Regards,