Got a peculiar problem!I have a task(say task1) that has been assigned a
resource , say 'A' and this task is marked done i.e it has both % complete
and % work complete set as 100%.Now I goto Tools >> Change Working Time and
change calendar timings for any resource other than 'A'.As soon as I do
this,the duration of task1 becomes 0 and task turns to milestone.Why is this
happening?I am not even changing the calendar of the resource that is
assigned to the task.
Also , this is happening only on machines that has MS Project 2003 with no
service pack.On machines with SP3 for MS Project 2003,such issue is not
encountered.
Thanks in Advance,
Vivek Gupta,
MCTS,Project 2007