We have an issue when we are saving dates in to resource availability, which
is probably due to a localisation issue but we can't pin point where the
actual issue is stemming from. We are located in Australia and the date
format is DD/MM/YYYY but when putting this in to project server in one
particular date field it is being reversed, regardless of what format it's
entered in. Steps to reproduce below. Any help appreciated.
1. In Project Server, I go to the resources view, select the resource and
click on “Edit Details”
2. In the “Earliest Available” field, I use the dropdown calendar to select
4 January 2010 (see note below)
3. I save using the “Save” button
4. I select “View Availability” so I can see a graph showing when the
resource is available and any task allocations
5. This view indicates the resource is available from 1 April 2010
Note: Also tried typing the date in as “01/04/2010” and “04/01/2010” with
same result – both these interpreted as 1 April 2010
Regards
Since this newsgroup is focus on sharepoint development issue, I suggest
you post the issue in the following technet forum so that more
sharepoint/project server professional guys can put in values on it:
#Project Server General
http://social.technet.microsoft.com/Forums/en/projectserver/threads
Sincerely,
Steven Cheng
Microsoft MSDN Online Support Lead
Delighting our customers is our #1 priority. We welcome your comments and
suggestions about how we can improve the support we provide to you. Please
feel free to let my manager know what you think of the level of service
provided. You can send feedback directly to my manager at:
msd...@microsoft.com.
--------------------
From: =?Utf-8?B?TWlsdG9uV2FkZGFtcw==?= <Milton...@noemail.noemail>
Subject: Sharepoint Portal Sever with Project Server Date Format Issue
Date: Fri, 11 Dec 2009 22:42:01 -0800
Hi,
We have an issue when we are saving dates in to resource availability,
which
is probably due to a localisation issue but we can't pin point where the
actual issue is stemming from. We are located in Australia and the date
format is DD/MM/YYYY but when putting this in to project server in one
particular date field it is being reversed, regardless of what format it's
entered in. Steps to reproduce below. Any help appreciated.
1. In Project Server, I go to the resources view, select the resource and
click on “Edit Details�?
2. In the “Earliest Available�?field, I use the dropdown calendar to
select
4 January 2010 (see note below)
3. I save using the “Save�?button
4. I select “View Availability�?so I can see a graph showing when the
resource is available and any task allocations
5. This view indicates the resource is available from 1 April 2010
Note: Also tried typing the date in as �?1/04/2010�?and
�?4/01/2010�?with
same result �?both these interpreted as 1 April 2010
Regards
That group is locked and marked as read only.
Could you suggest an appropriate alternative?
Regards.
""Steven Cheng"" wrote:
> click on “Edit Details�
>
> 2. In the “Earliest Available�field, I use the dropdown calendar to
> select
> 4 January 2010 (see note below)
>
> 3. I save using the “Save�button
>
> 4. I select “View Availability�so I can see a graph showing when the
> resource is available and any task allocations
>
> 5. This view indicates the resource is available from 1 April 2010
>
>
>
> Note: Also tried typing the date in as �1/04/2010�and
> �4/01/2010�with
> same result �both these interpreted as 1 April 2010
>
> Regards
>
>